Meeting Time and Place

Thursday Aug 26, 2010 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 428

Agenda

  • ESH&Q minute
  • Announcements
  • Lehman review preparations *
  • Solenoid Test Status *
  • Civil construction Status *

Outstanding Action Items

  • Determine new positions of cryo transfer line supports and feedback to civil (Jim/Tim)* Under work - needs to be settled within the next few weeks
  • Correct platform height and location for new expansion can (make sure there is room to stab u-tubes)(Jim/Rich)* Some work done, will review next week
  • Need to develop a leak check and assy plan for cryo lines (Jim/Tom) in work
  • Consult with Scot and Mark on cryo instrumentation (Jim) in work - met with J. Creel from cryo - P&I diagrams given for review
  • Look at getting traps/strainers for power supply LCW (Tom)
  • Identify PLC programmer to take over for Mark Wissman (Tim)
  • Need to put PR out for FDC techs (Tim)

Discussions

    • In attendance GW. Crahen, G. Biallas, J. Fochtman, T. Carstens, C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz, J. Foyles, M. Stevens, R. Bunton, G. Humble, C. Heck, D. Butler, K. Sullivan, Paul Collins, Tim Whitlatch