Line 3: Line 3:
 
* Install remaining CPUs
 
* Install remaining CPUs
 
* Readout FADC and F1 TDC crates
 
* Readout FADC and F1 TDC crates
 
  
 
==Chiller==
 
==Chiller==

Revision as of 09:19, 13 February 2014

DAQ

  • Initial readout of pedestals (3 crates)
  • Install remaining CPUs
  • Readout FADC and F1 TDC crates

Chiller

  • Make connections from chiller to manifold ring
  • Get power connections to chiller
  • Check operation of cooling loop

N2 flow

  • Install flow meters symmetrically on upstream and downstream

Slow Controls

  • Read back T and Humidity upstream
  • Read back T and Humidity downstream
  • Read back of RTDs on cooling plates upstream
  • Read back of RTDs on cooling plates downstream
  • Install interlock of chiller and MPPC power to humidity and temperature signals (long term). For now manual check.

Set Power MPPCs

  • Connection to network
  • Check that data base has correct bias information

LED monitoring

  • Replace translation boards with correct assignment
  • Install MOD crate
  • Complete cabling to crate
  • Connect MPOD and VME crates to network

Computers ?