==Notes by R. Jones==
 
==Notes by R. Jones==
 
===Report on the Installation Review===
 
===Report on the Installation Review===
: Tim
+
: Tim reported on the feedback received from the internal Installation and Safety Review of Hall D that took place last week at the lab.  The final report from the committee is available here [http://www.jlab.org/Hall-D/reviews/Installation_Feb09/Final%20Report%20on%20the%20Hall%20D%20Interim%20Installation%20Review_19%20Feb%202009.docx].  The first recommendation is that the Hall D group hire a technical work coordinator as soon as possible.  One outcome from the review is that we need better estimates of contributed manpower from universities in order to convince the reviewers at the Lehmann Review this summer that we are going to be able to do the construction and installation in the time that is shown on the schedule.
  
 
===Installation Schedule Version 1===
 
===Installation Schedule Version 1===

Revision as of 14:48, 26 February 2009

  • Time: 9:30 EST
  • Place: EVO and ESNET (with telephone bridge)
  • Connecting: instructions are here
  • Present: Richard J., Tim W., Alex S., Jim S., Franz K., and Eugene C.

Agenda

  1. Review of notes from last meeting - Richard
  2. Report on the Installation Review - Tim
  3. Version 1 installation schedule - Jim
  4. Update on the tagger background simulations - Alex
  5. Progress at BNL in laser ablation of diamonds - Richard
  6. Tagger dipole field uniformity specification - Jim
  7. Feedback on updated interface drawings - Tim
  8. Manpower for the spring 2009 CHESS run - Richard
  9. Plans for beam tests in 2010 - Franz

Notes by R. Jones

Report on the Installation Review

Tim reported on the feedback received from the internal Installation and Safety Review of Hall D that took place last week at the lab. The final report from the committee is available here [1]. The first recommendation is that the Hall D group hire a technical work coordinator as soon as possible. One outcome from the review is that we need better estimates of contributed manpower from universities in order to convince the reviewers at the Lehmann Review this summer that we are going to be able to do the construction and installation in the time that is shown on the schedule.

Installation Schedule Version 1

Jim walked us through the construction and installation schedule for the tagger and major photon beamline equipment [2].

Update on the tagger background simulations

Alex walked us through an early draft of his tagger background simulation technical note. [3]

Progress at BNL in laser ablation of diamonds

Richard presented some slides that John Smedley shared with him showing recent progress by the BNL group in thinning diamonds. [4]