Difference between revisions of "BLTWG Meeting 03/04/2013"

From GlueXWiki
Jump to: navigation, search
(Organization)
(Agenda)
Line 14: Line 14:
 
# Progress with the active collimator interface - ''Richard''
 
# Progress with the active collimator interface - ''Richard''
 
# Need for better documentation for interfaces - ''discussion''
 
# Need for better documentation for interfaces - ''discussion''
:* Active collimator electronics (power, shielding, cabling)
+
#* Active collimator electronics (power, shielding, cabling)
:* Microscope electronics (power, cooling, shielding, cabling)
+
#* Microscope electronics (power, cooling, shielding, cabling)
:* Microscope relocation plan (mechanisms, cable routing, clearances)
+
#* Microscope relocation plan (mechanisms, cable routing, clearances)
 
# Documenting our tagger magnet mapping plan - ''Tim''
 
# Documenting our tagger magnet mapping plan - ''Tim''
 
# Progress with tagger installation schedule - ''Tim''
 
# Progress with tagger installation schedule - ''Tim''
 
# [https://userweb.jlab.org/~dugger/triPol/mainz/MainzUpdate1.pdf Brief update on Mainz polarimeter] - ''Mike''
 
# [https://userweb.jlab.org/~dugger/triPol/mainz/MainzUpdate1.pdf Brief update on Mainz polarimeter] - ''Mike''
 
# ''any other business''
 
# ''any other business''

Revision as of 13:48, 4 March 2013

Organization

  • Time: 11:30 EST
  • Place: ESNET and Seevogh (Jlab community)
  • Connecting: instructions are here
  • Present: Richard J., Alex B., Brendan P., James M., Curtis M., Barry R., Igor S., Franz K., Mike D., Todd S., and Alex S.

Agenda

  1. Announcements
  2. Status of the CUA construction contract - Franz
  3. Status of the UConn construction contract - James, Alex
  4. Microscope alignment and control system - Richard
  5. Progress with pair spectrometer hodoscope - Alex
  6. Progress with the active collimator interface - Richard
  7. Need for better documentation for interfaces - discussion
    • Active collimator electronics (power, shielding, cabling)
    • Microscope electronics (power, cooling, shielding, cabling)
    • Microscope relocation plan (mechanisms, cable routing, clearances)
  8. Documenting our tagger magnet mapping plan - Tim
  9. Progress with tagger installation schedule - Tim
  10. Brief update on Mainz polarimeter - Mike
  11. any other business