BLTWG Meeting 07/09/2012

From GlueXWiki
Jump to: navigation, search
  • Time: 11:30 EST
  • Place: ESNET and EVO (with telephone bridge id 555 2690)
  • Connecting: instructions are here
  • Present: Mike D., Barry R., Dan S., Franz K., Alex S., Tim W., Yi Q., Curtis M., Richard J., Igor S., Brendan P., Fridah M., James M., Eugene C., and Alex B.

Agenda

  1. Announcements
  2. Progress on UConn construction contract -- Richard
    • July 3 -- Solicitation received at UConn !
    • July 20 -- Response from UConn to solicitation
  3. Progress on CUA construction contract -- Franz
  4. Requirements for low current operation -- Liping
  5. Study of the fixed tagger array geometry -- Dan
  6. Report from Glasgow group -- Ken
  7. Report from ASU group -- Mike
  8. Update on microscope construction -- James
    • possible loan of DAq system with FADC to UConn
    • possible swap of two SIPM's with Jlab (soon??)
  9. Plan for mapping the tagger magnet -- future discussion