Revision as of 10:47, 23 July 2012
- Time: 11:30 EST
- Place: ESNET and EVO (with telephone bridge id 561 3418)
- Connecting: instructions are here
- Present:
Agenda
- Announcements
- Progress on UConn construction contract -- Richard
- Requirements for low current operation -- discussion
- The fixed tagger array geometry -- Dan
- Report from Glasgow group -- Ken
- Report from ASU group -- Mike
- Update on microscope construction -- James
- possible loan of DAq system with FADC to UConn
- possible swap of two SIPM's with Jlab (soon??)
- Plan for mapping the tagger magnet -- future discussion