Difference between revisions of "BLTWG Meeting 08/20/2012"

From GlueXWiki
Jump to: navigation, search
(Created page with "* Time: 11:30 EST * Place: ESNET and EVO (with telephone bridge id 570 7748) * Connecting: instructions are here * Present: ---- ===Agen...")
 
(Agenda)
Line 9: Line 9:
 
#* possible loan of DAq system with FADC to UConn (in transit)
 
#* possible loan of DAq system with FADC to UConn (in transit)
 
#* two 50 micron SIPM's from Jlab (received)
 
#* two 50 micron SIPM's from Jlab (received)
 +
# Report from Sascha regarding activities at Jlab -- ''see below''
 +
 +
=== Notes ===
 +
Hello Richard,
 +
 +
I will not be able to attend our next beamline meeting.
 +
I am on vacations in Moscow now.
 +
 +
Here is a short update:
 +
 +
- I've sent an SOW draft to Franz and Dan about a week ago.
 +
  Almost all other docs for the contract are in place.
 +
 +
- I am preparing a collaboration MOU with ASU now. The draft
 +
  is almost ready
 +
 +
- Ivan from MEPhI is back to JLab. We are trying to finalize
 +
  the technical layout of the PS. I will order scint. tiles
 +
  and WLS fibers shortly.
 +
 +
- Hamamatsu said that they would be able to send a first article
 +
  of SiPMs (~200 pcs) to us in the beginning of November.

Revision as of 11:33, 20 August 2012

  • Time: 11:30 EST
  • Place: ESNET and EVO (with telephone bridge id 570 7748)
  • Connecting: instructions are here
  • Present:

Agenda

  1. Announcements
  2. Update on microscope construction -- Richard
    • possible loan of DAq system with FADC to UConn (in transit)
    • two 50 micron SIPM's from Jlab (received)
  3. Report from Sascha regarding activities at Jlab -- see below

Notes

Hello Richard,

I will not be able to attend our next beamline meeting. I am on vacations in Moscow now.

Here is a short update:

- I've sent an SOW draft to Franz and Dan about a week ago.

 Almost all other docs for the contract are in place.

- I am preparing a collaboration MOU with ASU now. The draft

 is almost ready

- Ivan from MEPhI is back to JLab. We are trying to finalize

 the technical layout of the PS. I will order scint. tiles
 and WLS fibers shortly. 

- Hamamatsu said that they would be able to send a first article

 of SiPMs (~200 pcs) to us in the beginning of November.