Difference between revisions of "Beam Test Meeting Mon. Mar. 12, 2012"
From GlueXWiki
(→Agenda) |
m (Text replacement - "/halldweb1.jlab.org/" to "/halldweb.jlab.org/") |
||
Line 3: | Line 3: | ||
# BCAL preparations | # BCAL preparations | ||
## [[BCAL Beam Tests 2012#Photos_and_Plots | Assembly Photos]] | ## [[BCAL Beam Tests 2012#Photos_and_Plots | Assembly Photos]] | ||
− | ## [https:// | + | ## [https://halldweb.jlab.org/elog-halld/SiPM/60 Electronics Update] (Fernando) |
Latest revision as of 11:35, 31 March 2015
Agenda
- BCAL preparations
- Assembly Photos
- Electronics Update (Fernando)
Minutes
FCAL
- the slot 9 adc was not properly seated in the 3.3 Gev runs, it is seated now
BCAL
- gluing of the light guides is done, they are slightly over sized
- plan is to set up in 126 within a week and install in the hall on March 21
Hall A Calorimeter
- plan is to put in hall by Mar 14 and slide under tagger on March 21
General info
- Sergey, Alex, and John will characterize the energy of the 3 remote paddles under the tagger on the floor
- Hall will be at 5 pass for remainder of run except for a week with a global energy change at some future date