# Planning for down time on Wednesday
 +
#* Remove pair spectrometer prototype from Hall (current in 60% position)
 +
#* Move Hall A prototype from 35% to 60% position
 +
#* Move Bcal prototype from 22% to 35% position
 +
#* Move Fcal prototype from 5% to 22% position
 
# Preliminary look at pulse heights and times (Elton)
 
# Preliminary look at pulse heights and times (Elton)
 
#* [[Media:Run491 histos.pdf]] Run 491 (Vbr=0.9 V)
 
#* [[Media:Run491 histos.pdf]] Run 491 (Vbr=0.9 V)
 
#* [[Media:Run498 histos.pdf]] Run 498 (Vbr=1.2 V)
 
#* [[Media:Run498 histos.pdf]] Run 498 (Vbr=1.2 V)
 +
# What gains do we want to run at?
 +
#* Gain Ratio (from Andrei's plot): Vbr=0.9/Vbr=1.2 = 1800/2500 = 0.72
 +
#* Maximum ADC from downstream ch2 R491/R498 = 3300/4000 = 0.83
 +
#[https://halldweb.jlab.org/wiki/images/c/c3/Fcal_range_484.ps FADC range from Run 484: Vbr=1.2V] (Andrei)
 +
# Bcal data to be taken
 +
#* TDC threshold scan
 +
#* Vover=1.2 V, 4 files 80k each, nominal TDC threshold
 +
#* Vover=0.9 V, 4 files 80k each, nominal TDC threshold
 +
#* Vover=1.2 V, 4 files 80k each, 1/2 TDC threshold
 +
#* Vover=0.9 V, 4 files 80k each, 1/2 TDC threshold
 +
#* Vover=1.2 V, 4 files 80k each, 1/4 TDC threshold
 +
#* Vover=0.9 V, 4 files 80k each, 1/4 TDC threshold
 +
# Considerations in choosing the SiPM operating voltage (Notes by Elton)
 +
#* PDE increases with overbias (favors 1.2 V)
 +
#* Noise increases with overbias (favors 0.9 V)
 +
#* Higher voltage decreases sensitivity to absolute bias voltage setting (favors 1.2 V)
 +
#* Gain increases with overbias, relaxing the electronic gain requirements (favors 1.2 V)
 +
 +
 +
== Minutes ==
 +
 +
FCAL
 +
 +
- time extraction mode still broken, hope to fix soon
 +
 +
- data taken at 7 degrees lower than nominal alignment
 +
 +
BCAL
 +
 +
- see above and logbook for more details
 +
 +
- data taking at 20 degree point complete
 +
 +
- will fix upstream electronics during beam studies on Wednesday
 +
 +
Overall
 +
 +
- will slide all detectors down 1 energy position on Wednesday
 +
 +
- FCAL to 22.8 %, BCAL to 35 %, Hall A to 50 %, pair spectrometer out

Latest revision as of 10:30, 31 March 2015

  1. Planning for down time on Wednesday
    • Remove pair spectrometer prototype from Hall (current in 60% position)
    • Move Hall A prototype from 35% to 60% position
    • Move Bcal prototype from 22% to 35% position
    • Move Fcal prototype from 5% to 22% position
  2. Preliminary look at pulse heights and times (Elton)
  3. What gains do we want to run at?
    • Gain Ratio (from Andrei's plot): Vbr=0.9/Vbr=1.2 = 1800/2500 = 0.72
    • Maximum ADC from downstream ch2 R491/R498 = 3300/4000 = 0.83
  4. FADC range from Run 484: Vbr=1.2V (Andrei)
  5. Bcal data to be taken
    • TDC threshold scan
    • Vover=1.2 V, 4 files 80k each, nominal TDC threshold
    • Vover=0.9 V, 4 files 80k each, nominal TDC threshold
    • Vover=1.2 V, 4 files 80k each, 1/2 TDC threshold
    • Vover=0.9 V, 4 files 80k each, 1/2 TDC threshold
    • Vover=1.2 V, 4 files 80k each, 1/4 TDC threshold
    • Vover=0.9 V, 4 files 80k each, 1/4 TDC threshold
  6. Considerations in choosing the SiPM operating voltage (Notes by Elton)
    • PDE increases with overbias (favors 1.2 V)
    • Noise increases with overbias (favors 0.9 V)
    • Higher voltage decreases sensitivity to absolute bias voltage setting (favors 1.2 V)
    • Gain increases with overbias, relaxing the electronic gain requirements (favors 1.2 V)


Minutes

FCAL

- time extraction mode still broken, hope to fix soon

- data taken at 7 degrees lower than nominal alignment

BCAL

- see above and logbook for more details

- data taking at 20 degree point complete

- will fix upstream electronics during beam studies on Wednesday

Overall

- will slide all detectors down 1 energy position on Wednesday

- FCAL to 22.8 %, BCAL to 35 %, Hall A to 50 %, pair spectrometer out