Difference between revisions of "CDC travel plans"

From GlueXWiki
Jump to: navigation, search
Line 26: Line 26:
 
#CDC mini-readout in EEL can be set up once FDC has moved into Hall D
 
#CDC mini-readout in EEL can be set up once FDC has moved into Hall D
 
#Expect CDC installation to be in Jan 2014? (from engineering schedule)
 
#Expect CDC installation to be in Jan 2014? (from engineering schedule)
 +
  
 
Equipment for readout
 
Equipment for readout
 
#4 long scint paddles are to travel down from CMU
 
#4 long scint paddles are to travel down from CMU
 
#Do we need to bring any NIM modules?
 
#Do we need to bring any NIM modules?

Revision as of 15:38, 7 October 2013

The plan

  1. Load up at CMU
  2. Ideally, store truck indoors overnight
  3. Drive to JLab
    1. Arrival before ?pm - go to EEL to unload
    2. Arrival after ? pm - go to Hall D, drive in, CDC in truck overnight, drive to EEL the next day and unload


Preparations:

  1. Add reinforcements to CDC cart for forklift
    1. Order materials for reinforcements
    2. Calculate position of CDC's CM
  2. Order swivel wheels
  3. Swap straight wheels for swivel wheels
  4. Rent a truck
    1. Need to measure temp near CDC - buy long thermocouple?
  5. Find somewhere to keep truck indoors overnight at CMU
  6. Negotiate loading bay access
  7. Check packing list, bring up to date
  8. Book accommodation at resfac


At JLab

  1. CDC is to be stored in EEL 126? until FDC installation is complete
  2. HV blocks need to be added
  3. CDC mini-readout in EEL can be set up once FDC has moved into Hall D
  4. Expect CDC installation to be in Jan 2014? (from engineering schedule)


Equipment for readout

  1. 4 long scint paddles are to travel down from CMU
  2. Do we need to bring any NIM modules?