CPP Run Coverage Summer 2022

From GlueXWiki
Revision as of 08:23, 11 May 2022 by Elton (Talk | contribs) (Created page with " {| class="wikitable" style="text-align: center;" |+ Time estimates for Run Plan |- ! Activity !! Duration (PAC Days) !! Duration (hours) !! Current !! Target !! Collimator...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search
Time estimates for Run Plan
Activity Duration (PAC Days) Duration (hours) Current Target Collimator Radiator Comment
Full target (Production) 20 960 27 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Alternate 0/90 deg diamond configuration
TOF, CDC HV Scans 0.2 10 27 nA - 3.4 mm AMO (1x10-4) Need time to assess data before updating settings. FCAL/BCAL trigger
Empty Target 1.5? 72 27 nA - 3.4 mm JD70-103 or JD70-107 Run at higher current?
Diamond Alignment 0.5? 24 20 nA Pb (0.3 mm) 3.4 mm JD70-103 and JD70-107
Trigger Commissioning 1? 48 100 nA? Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107
Lead Shield Alignment 0.2 10 30-100 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107
Beam Energy Calibration 0.1? 5 100 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Collimator Blocking for 5 min, periodically
Straight Track (Solenoid off) 0.5? 24 100 nA? Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Ramping magnet takes about a shift.
PS magnet at GlueX nominal current 0.1? 5 27 nA? Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107
TAC Runs 1.5? 72 <2 nA - 3.4 mm AMO (2x10-5)
All Non-production total 5.6 269 - - - - -