(Created page with "* Possible test schedule by Tim Media:CPP_Tests_Aug2020.pdf Assume that nominal the GlueX configuration consists of * No Pb shielding * DIRC installed * Solenoid field at...") |
|||
Line 22: | Line 22: | ||
# Configure experiment for CPP Test: 12 hours max | # Configure experiment for CPP Test: 12 hours max | ||
# Fill Target | # Fill Target | ||
− | |||
# Install 1 Pb sheet: 1 hr | # Install 1 Pb sheet: 1 hr | ||
+ | # Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr | ||
+ | # Install 0 Pb sheet: 1 hr | ||
# Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr | # Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr | ||
# Install 2 Pb sheets: 1 hr | # Install 2 Pb sheets: 1 hr | ||
# Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr | # Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr | ||
# Empty Target : 1 hr | # Empty Target : 1 hr | ||
− | |||
# Install 1 Pb sheet: 1 hr | # Install 1 Pb sheet: 1 hr | ||
+ | # Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr | ||
+ | # Install 0 Pb sheet: 1 hr | ||
# Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr | # Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr | ||
# Install 2 Pb sheets: 1 hr | # Install 2 Pb sheets: 1 hr | ||
Line 36: | Line 38: | ||
# Restore nominal GlueX configuration: 4 hours. | # Restore nominal GlueX configuration: 4 hours. | ||
− | Total time = | + | Total time = 32 hours |
The DIRC will have to be surveyed following the test. | The DIRC will have to be surveyed following the test. |
Revision as of 10:18, 15 July 2020
- Possible test schedule by Tim Media:CPP_Tests_Aug2020.pdf
Assume that nominal the GlueX configuration consists of
- No Pb shielding
- DIRC installed
- Solenoid field at 1350 A
CPP Test Configuration
- With and without Pb shielding
- DIRC removed
- Solenoid field at 1350 A (no change)
Screenshots of test layout media:CPP_Testconfig.jpg media:CPP_Testconfig2.jpg media:CPP_Testconfig3.jpg media:CPP_Testconfig4.jpg media:CPP_Testconfig5.jpg media:CPP_Testconfig6.jpg
Possible sequence and times
- CPP test DAQ setup: 2 hrs
- Data GlueX configuration - Full Target/DIRC (repeat from Dec 2019): 2 hrs
- Empty target
- Data GlueX configuration - Empty Target/DIRC : 1 hr
- Configure experiment for CPP Test: 12 hours max
- Fill Target
- Install 1 Pb sheet: 1 hr
- Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
- Install 0 Pb sheet: 1 hr
- Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr
- Install 2 Pb sheets: 1 hr
- Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
- Empty Target : 1 hr
- Install 1 Pb sheet: 1 hr
- Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
- Install 0 Pb sheet: 1 hr
- Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr
- Install 2 Pb sheets: 1 hr
- Data CPP Test Configuration - Empty Target/no DIRC/2Pb : 1 hr
- Fill Target
- Restore nominal GlueX configuration: 4 hours.
Total time = 32 hours
The DIRC will have to be surveyed following the test.