# Empty target
 
# Empty target
 
# Data GlueX configuration - Empty Target/DIRC : 1 hr
 
# Data GlueX configuration - Empty Target/DIRC : 1 hr
# Configure experiment for CPP Test: 12 hours max
+
# Configure experiment for CPP Test: 12 hr
# Fill Target
+
# Fill Target :
 
# Install 1 Pb sheet: 1 hr
 
# Install 1 Pb sheet: 1 hr
 
# Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
 
# Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
Line 28: Line 28:
 
# Install 2 Pb sheets: 1 hr
 
# Install 2 Pb sheets: 1 hr
 
# Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
 
# Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
# Empty Target : 1 hr
+
# Empty Target :
 
# Install 1 Pb sheet: 1 hr
 
# Install 1 Pb sheet: 1 hr
 
# Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
 
# Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
Line 39: Line 39:
  
 
Total time = 32 hours
 
Total time = 32 hours
 +
 +
Suggested personnel:
 +
* CPP will take necessary shifts during the test
 +
* May have up to 2 persons in the Counting Room and to install/remove Pb Sheets
  
 
The DIRC will have to be surveyed following the test.
 
The DIRC will have to be surveyed following the test.

Revision as of 11:22, 15 July 2020

Assume that nominal the GlueX configuration consists of

  • No Pb shielding
  • DIRC installed
  • Solenoid field at 1350 A

CPP Test Configuration

  • With and without Pb shielding
  • DIRC removed
  • Solenoid field at 1350 A (no change)
Screenshots of test layout media:CPP_Testconfig.jpg  media:CPP_Testconfig2.jpg
media:CPP_Testconfig3.jpg  media:CPP_Testconfig4.jpg 
media:CPP_Testconfig5.jpg  media:CPP_Testconfig6.jpg

Possible sequence and times

  1. CPP test DAQ setup: 2 hrs
  2. Data GlueX configuration - Full Target/DIRC (repeat from Dec 2019): 2 hrs
  3. Empty target
  4. Data GlueX configuration - Empty Target/DIRC : 1 hr
  5. Configure experiment for CPP Test: 12 hr
  6. Fill Target :
  7. Install 1 Pb sheet: 1 hr
  8. Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
  9. Install 0 Pb sheet: 1 hr
  10. Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr
  11. Install 2 Pb sheets: 1 hr
  12. Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
  13. Empty Target :
  14. Install 1 Pb sheet: 1 hr
  15. Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
  16. Install 0 Pb sheet: 1 hr
  17. Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr
  18. Install 2 Pb sheets: 1 hr
  19. Data CPP Test Configuration - Empty Target/no DIRC/2Pb : 1 hr
  20. Fill Target
  21. Restore nominal GlueX configuration: 4 hours.

Total time = 32 hours

Suggested personnel:

  • CPP will take necessary shifts during the test
  • May have up to 2 persons in the Counting Room and to install/remove Pb Sheets

The DIRC will have to be surveyed following the test.