(Created page with "* Possible test schedule by Tim Media:CPP_Tests_Aug2020.pdf Assume that nominal the GlueX configuration consists of * No Pb shielding * DIRC installed * Solenoid field at...")
 
Line 22: Line 22:
 
# Configure experiment for CPP Test: 12 hours max
 
# Configure experiment for CPP Test: 12 hours max
 
# Fill Target
 
# Fill Target
# Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
 
 
# Install 1 Pb sheet: 1 hr
 
# Install 1 Pb sheet: 1 hr
 +
# Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
 +
# Install 0 Pb sheet: 1 hr
 
# Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr
 
# Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr
 
# Install 2 Pb sheets: 1 hr
 
# Install 2 Pb sheets: 1 hr
 
# Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
 
# Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
 
# Empty Target : 1 hr
 
# Empty Target : 1 hr
# Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
 
 
# Install 1 Pb sheet: 1 hr
 
# Install 1 Pb sheet: 1 hr
 +
# Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
 +
# Install 0 Pb sheet: 1 hr
 
# Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr
 
# Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr
 
# Install 2 Pb sheets: 1 hr
 
# Install 2 Pb sheets: 1 hr
Line 36: Line 38:
 
# Restore nominal GlueX configuration: 4 hours.
 
# Restore nominal GlueX configuration: 4 hours.
  
Total time = 30 hours
+
Total time = 32 hours
  
 
The DIRC will have to be surveyed following the test.
 
The DIRC will have to be surveyed following the test.

Revision as of 11:18, 15 July 2020

Assume that nominal the GlueX configuration consists of

  • No Pb shielding
  • DIRC installed
  • Solenoid field at 1350 A

CPP Test Configuration

  • With and without Pb shielding
  • DIRC removed
  • Solenoid field at 1350 A (no change)
Screenshots of test layout media:CPP_Testconfig.jpg  media:CPP_Testconfig2.jpg
media:CPP_Testconfig3.jpg  media:CPP_Testconfig4.jpg 
media:CPP_Testconfig5.jpg  media:CPP_Testconfig6.jpg

Possible sequence and times

  1. CPP test DAQ setup: 2 hrs
  2. Data GlueX configuration - Full Target/DIRC (repeat from Dec 2019): 2 hrs
  3. Empty target
  4. Data GlueX configuration - Empty Target/DIRC : 1 hr
  5. Configure experiment for CPP Test: 12 hours max
  6. Fill Target
  7. Install 1 Pb sheet: 1 hr
  8. Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
  9. Install 0 Pb sheet: 1 hr
  10. Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr
  11. Install 2 Pb sheets: 1 hr
  12. Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
  13. Empty Target : 1 hr
  14. Install 1 Pb sheet: 1 hr
  15. Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
  16. Install 0 Pb sheet: 1 hr
  17. Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr
  18. Install 2 Pb sheets: 1 hr
  19. Data CPP Test Configuration - Empty Target/no DIRC/2Pb : 1 hr
  20. Fill Target
  21. Restore nominal GlueX configuration: 4 hours.

Total time = 32 hours

The DIRC will have to be surveyed following the test.