CPP Test 2020 - Schedule

From GlueXWiki
Revision as of 11:15, 15 July 2020 by Elton (Talk | contribs) (Created page with "* Possible test schedule by Tim Media:CPP_Tests_Aug2020.pdf Assume that nominal the GlueX configuration consists of * No Pb shielding * DIRC installed * Solenoid field at...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Assume that nominal the GlueX configuration consists of

  • No Pb shielding
  • DIRC installed
  • Solenoid field at 1350 A

CPP Test Configuration

  • With and without Pb shielding
  • DIRC removed
  • Solenoid field at 1350 A (no change)
Screenshots of test layout media:CPP_Testconfig.jpg  media:CPP_Testconfig2.jpg
media:CPP_Testconfig3.jpg  media:CPP_Testconfig4.jpg 
media:CPP_Testconfig5.jpg  media:CPP_Testconfig6.jpg

Possible sequence and times

  1. CPP test DAQ setup: 2 hrs
  2. Data GlueX configuration - Full Target/DIRC (repeat from Dec 2019): 2 hrs
  3. Empty target
  4. Data GlueX configuration - Empty Target/DIRC : 1 hr
  5. Configure experiment for CPP Test: 12 hours max
  6. Fill Target
  7. Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
  8. Install 1 Pb sheet: 1 hr
  9. Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr
  10. Install 2 Pb sheets: 1 hr
  11. Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
  12. Empty Target : 1 hr
  13. Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
  14. Install 1 Pb sheet: 1 hr
  15. Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr
  16. Install 2 Pb sheets: 1 hr
  17. Data CPP Test Configuration - Empty Target/no DIRC/2Pb : 1 hr
  18. Fill Target
  19. Restore nominal GlueX configuration: 4 hours.

Total time = 30 hours

The DIRC will have to be surveyed following the test.