Difference between revisions of "CPP and NPP Readiness Review"

From GlueXWiki
Jump to: navigation, search
(Documentation for Review)
(Documentation for Review)
Line 64: Line 64:
 
#* [https://userweb.jlab.org/~elton/ERR-CPP-NPP_docs/D00000-01-06-P006_RevB.docx FCAL Dark Room Procedure]
 
#* [https://userweb.jlab.org/~elton/ERR-CPP-NPP_docs/D00000-01-06-P006_RevB.docx FCAL Dark Room Procedure]
 
# [https://userweb.jlab.org/~elton/ERR-CPP-NPP_docs/Released_drawings Released Drawings]
 
# [https://userweb.jlab.org/~elton/ERR-CPP-NPP_docs/Released_drawings Released Drawings]
# Procedures for installation of muon detector
+
# [https://userweb.jlab.org/~elton/ERR-CPP-NPP_docs/Released_drawings/ Installation Schedule]
 
# Wiki Pages for further reference  
 
# Wiki Pages for further reference  
 
#* [[Charged Pion Polarizability Experiment in Hall-D | CPP wiki page]]
 
#* [[Charged Pion Polarizability Experiment in Hall-D | CPP wiki page]]
 
#* [[Pi0 Polarizability | NPP wiki page]]
 
#* [[Pi0 Polarizability | NPP wiki page]]

Revision as of 17:44, 5 February 2021

Preparations for the CPP and NPP Readiness Review

Planning for Experiment

Draft Outline Presentations (Feb 10)

  • Reviewers:
    • Stepan Stepanyan (chair+muon detector)
    • Alexandre Cansonne (Trigger)
    • Brad Sawatzky (Tracking System -MWPC)
    • Chris Keith (Target)
    • Robin Wines (Installation)
    • Mikhail Kostin (RadCon)
    • Edy Nissen (Beamline)
    • Javier Gomez (Observer)
    • Ed Folts (Observer)
  • Agenda
    • 08:15-08:45 Executive session
    • 08:45-09:35 (30+20) Overview of experiment and setup (Charges: 1, 2. 5, 8) -- Rory Miskimen
    • 09:35-10:25 (30+20) Engineering design and installation of the platform and muon chambers (Charges: 2, 3, 4) -- Tim Whitlatch
    • 10:25-10:45 Coffee break
    • 10:45-11:15 (20+10) Project implementation, resources and schedule (Charges: 3, 6, 7, 9) -- Elton Smith
    • 11:15-14:30 Lunch and Executive Session
    • 14:30 Closeout
  • ERR Final Report
  • Addressing ERR Review Recommendations

Additions to Standard Equipment

The major modifications required to operate the experiment are the following

  • Design, fabrication and installation of the muon detector
    • Multi-wire proportional chambers
    • Modifications to the downstream platform, support structure and iron absorbers
  • New (mono-isotopic) solid Pb target
  • Charged-particle trigger based on the time-of-flight detectors
  • Move tagger microscope to cover 6 GeV coherent peak

Documentation for Review

  1. PAC Documents
  2. TOF Trigger
  3. Draft Documents
  4. Released Drawings
  5. Installation Schedule
  6. Wiki Pages for further reference