'''Agenda'''
 
'''Agenda'''
  
* Moving status - Scot, Mark S, Elliott
+
* Controls installation status - Scot, Mark S, Elliott
 
** racks and computers
 
** racks and computers
 
** power
 
** power
 
** networking
 
** networking
 
** telephone
 
** telephone
* Coil test plan - Josh
 
 
* Magnet power supply and interlock commissioning - Cody
 
* Magnet power supply and interlock commissioning - Cody
 
** flow pressure and rates, flow switches
 
** flow pressure and rates, flow switches
Line 22: Line 21:
 
* PLC programming/testing status - Mark W
 
* PLC programming/testing status - Mark W
 
** what else is left to do besides testing?
 
** what else is left to do besides testing?
 +
** backup PLC programmer?
 
* UPS status - Mark W, Elliott
 
* UPS status - Mark W, Elliott
 
** relay modules, use in interlock system
 
** relay modules, use in interlock system
Line 33: Line 33:
 
** Two weeks notice to Errol - when?
 
** Two weeks notice to Errol - when?
 
** backup power in Test Lab?
 
** backup power in Test Lab?
 +
* Test plan - Josh
 
* Coil repair status - George
 
* Coil repair status - George
 
* OSP documents and review - Elliott, George
 
* OSP documents and review - Elliott, George

Latest revision as of 13:41, 27 July 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 29-Jul-2010 9:30am ARC 428


Agenda

  • Controls installation status - Scot, Mark S, Elliott
    • racks and computers
    • power
    • networking
    • telephone
  • Magnet power supply and interlock commissioning - Cody
    • flow pressure and rates, flow switches
    • interlock on strain gauges?
  • Controls racks - Scot
    • what else is left to do?
  • PLC programming/testing status - Mark W
    • what else is left to do besides testing?
    • backup PLC programmer?
  • UPS status - Mark W, Elliott
    • relay modules, use in interlock system
    • connection to PLC?
  • EPICS <--> PLC communications - Wesley, Elliott
    • connection to guard shack
  • HMI and EWEB programming - Yi, Elliott
  • Installation status - George, Mark S
    • rigging, platform and stand, etc.
    • cryo can
    • Two weeks notice to Errol - when?
    • backup power in Test Lab?
  • Test plan - Josh
  • Coil repair status - George
  • OSP documents and review - Elliott, George