Commissioning Calibration Data

From GlueXWiki
Revision as of 18:44, 22 September 2015 by Sdobbs (Talk | contribs) (Fall 2015)

Jump to: navigation, search

Fall 2015

Calibration data needs as of Sept. 22, 2015

Detector Status Data in Hand Est. Data Needed Est. Running Time Notes
BCAL More Needed 1.3 M (pi0, cluster > 350 MeV) 100x
CDC More Needed
FCAL More Needed 18k 10x
FDC More Needed 3 shifts, 10^-4 radiator, 100 nA, no field needed
PS/PSC OK
Start Counter More Needed 75 M 20x basic calibrations are good, more refinement possible
TAGH OK
TAGM More Needed 10 M - 50 M
TOF OK need to verify stability of calibrations with more data