Line 3: | Line 3: | ||
** PXI spare controller procurement (Brian) | ** PXI spare controller procurement (Brian) | ||
* Atmospheric pressure sensors (Bobby, Brian) | * Atmospheric pressure sensors (Bobby, Brian) | ||
− | * FCAL chiller controls (Scot, Bobby) | + | * FCAL-2 chiller controls (Scot, Bobby) |
+ | * FCAL-2 sensors (Bobby) | ||
+ | * FCAL-2 voltage controls (Hovanes) | ||
* CAEN HV crate reset for T1-8-TOP and D2-8-TOP (Hovanes, Bobby) | * CAEN HV crate reset for T1-8-TOP and D2-8-TOP (Hovanes, Bobby) | ||
* Alarms for "GAS:i::FDC_CDC_Pressure-PT500" PV (Scot, Bobby) | * Alarms for "GAS:i::FDC_CDC_Pressure-PT500" PV (Scot, Bobby) |
Revision as of 14:37, 26 September 2023
- Announcements
- Solenoid status
- PXI spare controller procurement (Brian)
- Atmospheric pressure sensors (Bobby, Brian)
- FCAL-2 chiller controls (Scot, Bobby)
- FCAL-2 sensors (Bobby)
- FCAL-2 voltage controls (Hovanes)
- CAEN HV crate reset for T1-8-TOP and D2-8-TOP (Hovanes, Bobby)
- Alarms for "GAS:i::FDC_CDC_Pressure-PT500" PV (Scot, Bobby)
- New NMR probe (Scot)
- Switch in the tagger hall (Hovanes)
- Other items
Time/Location
10:00am Thursday 28-September-2023