=Minutes=
 
=Minutes=
 +
 +
Present:  Elliott W, Mark S, Scot S, Josh B.
 +
 +
 +
'''Target'''
 +
 +
We discussed Chris Keith's note concerning UPS power and controllers he plans to use.  The refrigerator takes way too much power to put on the UPS, and the target would warm up slowly anyway.  He wants the monitoring devices on UPS power but they don't use much.  One concern is that when possible he should use devices compatible with what we already have.
 +
 +
 +
 +
'''UPS Power'''
 +
 +
The UPS needs 480V run from the utility room to the Rack Room.  It is not clear whether we need to run UPS power to the hall, we might just use spot UPS's.  It all depends on the total UPS load in the hall, the cost of small UPS's, and the cost of running power down and installing a panel.
 +
 +
 +
 +
'''Accel

Revision as of 17:24, 10 February 2012

Agenda

  • Announcements
  • Minutes from previous meeting 26-Jan-2012
  • Meeting with Accelerator and halls - Hovanes, Elliott
  • Counting house installation, power, UPS power, etc. - Hovanes, Elliott
  • Equipment orders - Mark, others
  • Solenoid_Controls_Redesign - Mark, Josh, Scot, Yi, Elliott
    • QD, shunt, ground fault detector, racks, UPS power to racks
    • coil inductances, schematics, etc. - Scot
    • fast/slow DAQ integration, Labview licenses - Yi, Elliott
  • Experiment Control Supervisor - Vardan, Hovanes, Elliott
  • EPICS - Hovanes, Nerses
    • archiver, alarm system, scalers
  • Test stand - Hovanes, Josh
  • Target, goniometer, other new systems - Hovanes, Elliott
  • PLC programming - Josh
    • A-B class, program redesign, new features, new computer
  • Elogs and databases - Elliott
    • Midas elog
    • Operator elog
    • inventory database - IRMIS, CLAS, other?
  • Mantis task tracker


Time/Location

9:30 AM Thurs 9-Feb-2012 CC L207


Announcements

Next Meeting

9:30am 23-Feb-2012 CC L207


Minutes

Present: Elliott W, Mark S, Scot S, Josh B.


Target

We discussed Chris Keith's note concerning UPS power and controllers he plans to use. The refrigerator takes way too much power to put on the UPS, and the target would warm up slowly anyway. He wants the monitoring devices on UPS power but they don't use much. One concern is that when possible he should use devices compatible with what we already have.


UPS Power

The UPS needs 480V run from the utility room to the Rack Room. It is not clear whether we need to run UPS power to the hall, we might just use spot UPS's. It all depends on the total UPS load in the hall, the cost of small UPS's, and the cost of running power down and installing a panel.


Accel