Difference between revisions of "DIRC Planning for FY16"
From GlueXWiki
Line 12: | Line 12: | ||
** Is additional support for engineering time at MIT needed? | ** Is additional support for engineering time at MIT needed? | ||
** Design review by JLab (ie. Tim et. al.): assume ~4 weeks | ** Design review by JLab (ie. Tim et. al.): assume ~4 weeks | ||
− | * Milestone: Fabrication start August-September 2016 | + | * '''Milestone''': Fabrication start August-September 2016 |
** Get started on contract with MIT: Statement of Work and Sole Source Justification | ** Get started on contract with MIT: Statement of Work and Sole Source Justification | ||
Revision as of 09:39, 15 January 2016
Support Structure
- Milestone: Design finalized May-June 2016
- Optical box length needed to determine how they will be supported
- Design review by JLab (ie. Tim et. al.): assume ~4 weeks
- Milestone: Fabrication start July-August 2016
- Get started on contract with IU: Statement of Work and Sole Source Justification
Optical Boxes
- Milestone: Design finalized June-July 2016
- Is additional support for engineering time at MIT needed?
- Design review by JLab (ie. Tim et. al.): assume ~4 weeks
- Milestone: Fabrication start August-September 2016
- Get started on contract with MIT: Statement of Work and Sole Source Justification
Electronics
- Milestone: ASIC and Adapter board order submitted July-August 2016
- Some delay in MAROC chip packaging, so CLAS order of ASIC and Adapter boards may be delayed.
- Opportunity: Possible use of FPGA boards from CLAS
- The FPGA boards for CLAS were produced with wrong hole size, but could be used for GlueX.
- Could assemble boards ~now. Waiting for quote from vendor to evaluate cost reduction.
Transportation
- Milestone: Shipping crate design finalized October 2016
- Technically FY17, but considering additional transportation tests planed, should we start earlier?