(Action Items from previous meetings)
(Action Items from previous meetings)
Line 5: Line 5:
 
# Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi)
 
# Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi)
 
# Determine granularity of LED bias and power, as well as multiplicity of trigger signals (Elton)
 
# Determine granularity of LED bias and power, as well as multiplicity of trigger signals (Elton)
 +
# Check on official releases of the 3D model (Elton and Jim)
  
 
== Tentative Agenda ==
 
== Tentative Agenda ==

Revision as of 09:59, 2 November 2012

Action Items from previous meetings

  1. Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando)
  2. Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim)
  3. Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi)
  4. Determine granularity of LED bias and power, as well as multiplicity of trigger signals (Elton)
  5. Check on official releases of the 3D model (Elton and Jim)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule for production and testing (all)
  4. mini-Bcal (Elton)
  5. SiPM production testing (Yi)
  6. Mechanical assembly (Jim)
  7. Temperature compensation (Jack)
  8. Electronic boards (Fernando and Chris)
  9. Light guide gluing setup (Scot)

Minutes

Attending: