Difference between revisions of "Dec 8, 2008 Calorimetry"
From GlueXWiki
(→Tentative Agenda) |
(→Tentative Agenda (Emphasis is Calibration)) |
||
Line 30: | Line 30: | ||
# BCAL | # BCAL | ||
## [[Fiber Test with SiPM | Testing of fibers with SiPM readout and Sr90 source]] (Beni) | ## [[Fiber Test with SiPM | Testing of fibers with SiPM readout and Sr90 source]] (Beni) | ||
+ | ## Lead Specification (Elton) | ||
## Magnetic Field Update (JLab) | ## Magnetic Field Update (JLab) | ||
## Other updates | ## Other updates |
Revision as of 14:10, 1 December 2008
Time: 11:15 ET.
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 39527048# (remember the "#")
Contents
Items for followup from Nov 24 meeting
- Updates on Calibration Specification Table.
- Resolution studies (Blake)
- Develop criteria for evaluating resolution studies
- Study impact of inactive material at the end of Bcal on acceptance.
- Add F100 rad hard glass to simulation. - New graduate student has been assigned this project.
- Add roadmap for Bcal Roadmap to wiki (Elton)
- Check what configuration (thresholds, step sizes, stack? parameters for secondaries, etc) is being used for the Hall D simulations (Regina)
- Updated schedule with new Fcal procurement dates. (Elke will send this to Matt)
- Report on the Bfield components in the region of the Bcal reaout (JLab for next meeting).
- Updated drawings of Bcal modules (including O-ring) for discussions. Tim will see if that can be fitted into designer tasks.
Documents to Review
- Calibration/monitoring update Athens: Media:APD_vs_tube_linearity.ppt
Tentative Agenda (Emphasis is Calibration)
- Announcements
- Calibration
- Progress on filling in the Calibration Specification Table.
- FCAL Update
- BCAL
- Testing of fibers with SiPM readout and Sr90 source (Beni)
- Lead Specification (Elton)
- Magnetic Field Update (JLab)
- Other updates
- Any other business
Minutes
Attending: