Difference between revisions of "December 17, 2018 DIRC"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 25: Line 25:
 
#* LED fiber feedthroughs and diffuser
 
#* LED fiber feedthroughs and diffuser
 
#** Fiber mount location (Bill/Stephanie) [https://halldweb.jlab.org/wiki/images/3/3c/Image005.png]
 
#** Fiber mount location (Bill/Stephanie) [https://halldweb.jlab.org/wiki/images/3/3c/Image005.png]
 +
#** Feedthrough solution: https://halldweb.jlab.org/DocDB/0035/003581/002/DIRC_Meeting_LED_defuser_Dec_17_2018.pdf
 
#* Testing at JLab:
 
#* Testing at JLab:
 
#** Laser alignment test in ESB: lower box complete, upper box waiting for flange (Bill)
 
#** Laser alignment test in ESB: lower box complete, upper box waiting for flange (Bill)

Revision as of 14:08, 17 December 2018

Meeting Information

GlueX DIRC Meeting
Monday December 17, 2018
1:00 pm, EDT
JLab room F326

Connection Using Bluejeans

  1. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
  2. To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
  3. To join via phone, use one of the following numbers and the Conference ID: 846453895
    • US or Canada: +1 408 740 7256 or
    • US or Canada: +1 888 240 2560
  4. More information on connecting to bluejeans is available.

Agenda

  1. Announcements
    • Last meeting of 2018, next meeting January 7th @ 1 pm. After that will need to find new time slot for Spring, expect a Doodle poll.
  2. Optical box
  3. Installation schedule (Tim)
  4. Software/simulations
    • Finalizing DIRC "as-built" geometry: bar box internals, etc. (Yunjie)
    • LED generator and timing calibration (Yunjie)
    • Time-based studies and adding # photons to LUT likelihood (Maria)
    • Alignment updates (Cris)
    • Software overview and tasks (All)
      • Many recent updates to dirc_commissioning_2018 branches to include flag for reflected photons, switch to plexiglass window, and add DIRC hits to REST format and analysis Three output for faster iterations during commissioning in February.
  5. Addressing ERR review recommendations
    • Recommendations pertaining to DIRC commissioning should be addressed before installation.
  6. AOB