== Agenda ==
 
== Agenda ==
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php?title=December_3,_2020_CPP_Design_Meeting&action=edit&section=2
+
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/December_17,_2020_CPP_Design_Meeting
 
* Readiness Review
 
* Readiness Review
 
* Schedule [[Media:CPP_Schedule.pdf]]
 
* Schedule [[Media:CPP_Schedule.pdf]]

Revision as of 16:05, 16 December 2020

Meeting Time and Place

Thursday Dec 17, 2020, 2pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S

Agenda

  • Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/December_17,_2020_CPP_Design_Meeting
  • Readiness Review
  • Schedule Media:CPP_Schedule.pdf
  • Solid Pb target support and installation
  • Beam vacuum pipe needed for the experiment. (Target is located at z=1 cm, 64 cm upstream of nominal GlueX)
  • Relocation of CDC FADC electronics for use with the muon chamber
  • Review that there are no interferences for the new grounding shields for the muon chamber electronics.
  • Design/Procurement status
  • Things to work out
    • Gas line manifold
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements

Minutes and Action Items

  • Request for ERR submitted
  • We need to show that everything is in place for a successful experiment
    • Design status
    • Procurement schedule/status
    • Installation schedule
      • For installing prior to 2022 run - full detector then uninstall a portion to run Primex
      • For Installing in middle of 2022 run
    • Installation procedure
    • Manpower availability
    • Calibration and Analysis procedures
    • Need Safety documents
    • OSP
    • Installation procedure/HDlist
    • EESAD
    • COO
  • Will use CDC Gas system and crates
  • Signal cables needed
  • Elton to write OSP
  • Elton to start ERR web page (use DIRC as an example)
  • Tim to update install schedule to show 2 scenarios
  • Tim to Start installation plan
  • Rory to get wire chambers working
  • Tim and Stephanie to complete support stand drawing package