Revision as of 08:09, 17 December 2020
Meeting Time and Place
Thursday Dec 17, 2020, 2pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/December_3,_2020_CPP_Design_Meeting
- Readiness Review
- Schedule Media:CPP_Schedule.pdf
- Solid Pb target support and installation
- Beam vacuum pipe needed for the experiment. (Target is located at z=1 cm, 64 cm upstream of nominal GlueX)
- Relocation of CDC FADC electronics for use with the muon chamber Media:CPP_Electronics_enclosure.pdf
- Review that there are no interferences for the new grounding shields for the muon chamber electronics.
- Design/Procurement status
- Things to work out
- Gas line manifold
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
Minutes and Action Items
- Request for ERR submitted
- We need to show that everything is in place for a successful experiment
- Design status
- Procurement schedule/status
- Installation schedule
- For installing prior to 2022 run - full detector then uninstall a portion to run Primex
- For Installing in middle of 2022 run
- Installation procedure
- Manpower availability
- Calibration and Analysis procedures
- Need Safety documents
- OSP
- Installation procedure/HDlist
- EESAD
- COO
- Will use CDC Gas system and crates
- Signal cables needed
- Elton to write OSP
- Elton to start ERR web page (use DIRC as an example)
- Tim to update install schedule to show 2 scenarios
- Tim to Start installation plan
- Rory to get wire chambers working
- Tim and Stephanie to complete support stand drawing package