Difference between revisions of "December 22,2010 Tracking CDC/FDC"

From GlueXWiki
Jump to: navigation, search
(CDC Update)
Line 24: Line 24:
  
 
=== CDC Update ===
 
=== CDC Update ===
 +
 +
Curtis gave an update on the construction status:
 +
 +
the spec for the electrical hookups is being discussed with Tim et al.
 +
 +
the 7th row of straws is nearly complete. The 8th row will be started after the holiday break and will complete that block of stereo straws. Curtis is to be trained in straw fitting training this afternoon as a contingency worker because installing the straws requires 3 people working together. (In fact both Curtis and Naomi did this).  It takes about 1.5h to install 30 straws.  Most of the other steps in the construction just require 1 person at a time.
 +
 +
The plastic feedthrus and donuts have been checked with 100% acceptance.  About half of the pin-holders have been checked; all but one (which was squashed) have been accepted.  The accepted parts have been cleaned and are in storage in the cleanroom.

Revision as of 10:17, 23 December 2010

Meeting Time and Place

Wednesday December 22, 2010 at 11:00am At Jefferson Lab, the meeting will be held in F326

Connections

To connect from the outside, please use ESNET
1.) ESNET: 8542553
2.) Phone:
+1-800-377-8846 : US
+1-888-276-7715 : Canada
+1-302-709-8424 : International
then enter participant code: 77438230# (remember the "#")

Agenda

  1. Announcements
  2. FDC Update logbook
  3. CDC Update [1]

Minutes

Participants: Curtis, Naomi, Eugene, Beni, Mark, and Lubomir.

CDC Update

Curtis gave an update on the construction status:

the spec for the electrical hookups is being discussed with Tim et al.

the 7th row of straws is nearly complete. The 8th row will be started after the holiday break and will complete that block of stereo straws. Curtis is to be trained in straw fitting training this afternoon as a contingency worker because installing the straws requires 3 people working together. (In fact both Curtis and Naomi did this). It takes about 1.5h to install 30 straws. Most of the other steps in the construction just require 1 person at a time.

The plastic feedthrus and donuts have been checked with 100% acceptance. About half of the pin-holders have been checked; all but one (which was squashed) have been accepted. The accepted parts have been cleaned and are in storage in the cleanroom.