=== FDC Update ===
 +
 +
Lubomir reported on FDC construction and presented gas gain measurements and Garfield calculations for several Ar/CO2/CH4 mixtures.
  
 
=== CDC Update ===
 
=== CDC Update ===
Line 27: Line 31:
 
Curtis gave an update on the construction status:
 
Curtis gave an update on the construction status:
  
the spec for the electrical hookups is being discussed with Tim et al.
+
*The spec for the electrical hookups is undergoing discussion.
 +
 
 +
*The 7th row of straws is nearly complete.  The 8th row will be started after the holiday break and will complete that block of stereo straws.  Curtis is to be trained in straw fitting training this afternoon as a contingency worker because installing the straws requires 3 people working together.  (Curtis and Naomi both did this).  It takes about 1.5h to install 30 straws.  Most of the other steps in the construction just require 1 person at a time.
 +
 
 +
*The plastic feedthrus and donuts have been checked with 100% acceptance.  About half of the pin-holders have been checked; all but one (which was squashed) have been accepted.  The accepted parts have been cleaned and are in storage in the cleanroom.
 +
 
 +
*After the first batch of straws, no more resistance issues have been encountered.  The resistance of each straw (+donut+feedthru) assembly glued into the chamber has been acceptable.
  
the 7th row of straws is nearly complete. The 8th row will be started after the holiday break and will complete that block of stereo straws. Curtis is to be trained in straw fitting training this afternoon as a contingency worker because installing the straws requires 3 people working together. (In fact both Curtis and Naomi did this).  It takes about 1.5h to install 30 straws.  Most of the other steps in the construction just require 1 person at a time.
+
*We are waiting to hear a date for delivery of the next batch of straws.
  
The plastic feedthrus and donuts have been checked with 100% acceptance.  About half of the pin-holders have been checked; all but one (which was squashed) have been accepted.  The accepted parts have been cleaned and are in storage in the cleanroom.
+
fADC

Revision as of 10:37, 23 December 2010

Meeting Time and Place

Wednesday December 22, 2010 at 11:00am At Jefferson Lab, the meeting will be held in F326

Connections

To connect from the outside, please use ESNET
1.) ESNET: 8542553
2.) Phone:
+1-800-377-8846 : US
+1-888-276-7715 : Canada
+1-302-709-8424 : International
then enter participant code: 77438230# (remember the "#")

Agenda

  1. Announcements
  2. FDC Update logbook
  3. CDC Update [1]

Minutes

Participants: Curtis, Naomi, Eugene, Beni, Mark, and Lubomir.

FDC Update

Lubomir reported on FDC construction and presented gas gain measurements and Garfield calculations for several Ar/CO2/CH4 mixtures.

CDC Update

Curtis gave an update on the construction status:

  • The spec for the electrical hookups is undergoing discussion.
  • The 7th row of straws is nearly complete. The 8th row will be started after the holiday break and will complete that block of stereo straws. Curtis is to be trained in straw fitting training this afternoon as a contingency worker because installing the straws requires 3 people working together. (Curtis and Naomi both did this). It takes about 1.5h to install 30 straws. Most of the other steps in the construction just require 1 person at a time.
  • The plastic feedthrus and donuts have been checked with 100% acceptance. About half of the pin-holders have been checked; all but one (which was squashed) have been accepted. The accepted parts have been cleaned and are in storage in the cleanroom.
  • After the first batch of straws, no more resistance issues have been encountered. The resistance of each straw (+donut+feedthru) assembly glued into the chamber has been acceptable.
  • We are waiting to hear a date for delivery of the next batch of straws.