==Outstanding Action Items==
 
==Outstanding Action Items==
  
*</strike>Complete Power OSP for solenoid test (all)</strike>
+
*<strike>Complete Power OSP for solenoid test (all)</strike>
 
* Need list of people needing access to the ESB (Rad area and building owner is FM)
 
* Need list of people needing access to the ESB (Rad area and building owner is FM)
 
* Coil 3 in ESB requires property storage request
 
* Coil 3 in ESB requires property storage request
Line 31: Line 31:
 
==Discussions==
 
==Discussions==
  
 +
**In attendance W. Crahen,  J. Fochtman,  C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz,  C. Heck, D. Butler, K. Sullivan,  W. Sachleben, A. Johnson, Tim Whitlatch
  
 
+
* Solenoid cooling back down after attempt to remove ice ball in vapor cooled lead flow
**In attendance W. Crahen,  J. Fochtman,  C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz,  C. Heck, D. Butler, K. Sullivan,  W. Sachleben, A. Johnson, Tim Whitlatch
+
* Need to enter coil 3 in HDlist - bring right into test lab
 +
* need to get dipole (for sweep magnet) from FEL - Jim Coleman
 +
* need to look at organizing someone to take care of material handling for Hall D. Can we use the transportainer?
 +
* order flat screen for solenoid test area
  
 
==New Action Items==
 
==New Action Items==

Latest revision as of 08:52, 10 December 2010

Meeting Time and Place

Friday Dec 3, 2010 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 428

Agenda

  • ESH&Q minute COO in Hall D
  • Announcements
    • training
    • Christmas Luncheon
  • Lehman Review Dec 7 *
  • Solenoid Test Status *
  • Civil construction Status
  • Infrastructure plans
  • FDC construction preparations
  • CDC status
  • BCAL readout
  • Platforms
  • CAD update
  • Space issues (ESB, trailer, 2nd floor ARC )
  • 2011 and future work
  • Manpower (Eng,Tech,Des)

Outstanding Action Items

  • Complete Power OSP for solenoid test (all)
  • Need list of people needing access to the ESB (Rad area and building owner is FM)
  • Coil 3 in ESB requires property storage request
  • Put in req for 4 techs for solenoid and installation Req issued and approved by Eugene waiting physics division approval

Discussions

    • In attendance W. Crahen, J. Fochtman, C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz, C. Heck, D. Butler, K. Sullivan, W. Sachleben, A. Johnson, Tim Whitlatch
  • Solenoid cooling back down after attempt to remove ice ball in vapor cooled lead flow
  • Need to enter coil 3 in HDlist - bring right into test lab
  • need to get dipole (for sweep magnet) from FEL - Jim Coleman
  • need to look at organizing someone to take care of material handling for Hall D. Can we use the transportainer?
  • order flat screen for solenoid test area

New Action Items