(Minutes and Action Items)
(Minutes and Action Items)
 
Line 30: Line 30:
 
** OSP
 
** OSP
 
** Installation procedure/HDlist
 
** Installation procedure/HDlist
 +
** EESAD
 +
** COO
 +
 +
* Will use CDC Gas system and crates
 +
* Signal cables needed
 +
* Elton to write OSP
 +
* Elton to start ERR web page (use DIRC as an example)
 +
* Tim to update install schedule to show 2 scenarios
 +
* Tim to Start installation plan
 +
* Rory to get wire chambers working
 +
* Tim and Stephanie to complete support stand drawing package

Latest revision as of 16:11, 7 December 2020

Meeting Time and Place

Thursday Dec 03, 2020, 2pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S

Agenda

  • Things to work out
    • Gas line manifold
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements

Minutes and Action Items

  • Request for ERR submitted
  • We need to show that everything is in place for a successful experiment
    • Design status
    • Procurement schedule/status
    • Installation schedule
      • For installing prior to 2022 run - full detector then uninstall a portion to run Primex
      • For Installing in middle of 2022 run
    • Installation procedure
    • Manpower availability
    • Calibration and Analysis procedures
    • Need Safety documents
    • OSP
    • Installation procedure/HDlist
    • EESAD
    • COO
  • Will use CDC Gas system and crates
  • Signal cables needed
  • Elton to write OSP
  • Elton to start ERR web page (use DIRC as an example)
  • Tim to update install schedule to show 2 scenarios
  • Tim to Start installation plan
  • Rory to get wire chambers working
  • Tim and Stephanie to complete support stand drawing package