https://halldweb.jlab.org/wiki/index.php?title=Draft_Start_Counter_Commissioning_Plan&feed=atom&action=historyDraft Start Counter Commissioning Plan - Revision history2024-03-28T12:48:55ZRevision history for this page on the wikiMediaWiki 1.24.1https://halldweb.jlab.org/wiki/index.php?title=Draft_Start_Counter_Commissioning_Plan&diff=59529&oldid=prevMarki: Created page with "<pre> Subject: Start Counter Commissioning Plan Date: Fri, 8 Aug 2014 21:19:00 +0000 From: Werner Boeglin <boeglinw@fiu.edu> To: Mark M. Ito <marki@jlab.org> Hi Mark, her..."2014-08-12T19:09:06Z<p>Created page with "<pre> Subject: Start Counter Commissioning Plan Date: Fri, 8 Aug 2014 21:19:00 +0000 From: Werner Boeglin <boeglinw@fiu.edu> To: Mark M. Ito <marki@jlab.org> Hi Mark, her..."</p>
<p><b>New page</b></p><div><pre><br />
Subject: Start Counter Commissioning Plan<br />
Date: Fri, 8 Aug 2014 21:19:00 +0000<br />
From: Werner Boeglin <boeglinw@fiu.edu><br />
To: Mark M. Ito <marki@jlab.org><br />
<br />
Hi Mark,<br />
<br />
here is a possible plan for commissioning:<br />
<br />
After installation<br />
- Are all TDC and ADC channels connected<br />
- MPOD control working<br />
<br />
With Cosmic<br />
- ADC and TDC histograms filled and displaid for all 30 channels<br />
- Verify TDC and ADC spectra with data previously taken at FIU<br />
<br />
With Beam<br />
- raw ADC , TDC spectra. <br />
- include tracking information for time propagation correction<br />
- determine time difference between RF and start counter (corrected)<br />
- optimize time resolution (individual offsets, walk corrections)<br />
- determine start counter solid angle coverage.<br />
- develop standard calibration and monitoring procedures<br />
<br />
kind regards<br />
<br />
Werner<br />