Fall 2016 Run time charts

From GlueXWiki
Revision as of 08:20, 8 December 2016 by Deurpam (Talk | contribs) (Runplan time charts)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Runplan time charts

Commissioning time chart:
Fall16 week1.jpg

Commissioning time chart. Week 1. Time t=0 corresponds to 12/13/2016. The horizontal scale is the time during which beam is available (in other word, it would be the real time with 100% of beam efficiency). The task time estimates given on the plot have 100% contingency.