Difference between revisions of "Fall 2019 Commissioning Meetings"

From GlueXWiki
Jump to: navigation, search
(Thursday, December 19)
(Thursday, December 19)
Line 28: Line 28:
 
** Time over threshold analysis - [https://halldweb.jlab.org/DocDB/0042/004295/001/DIRC_tot_slides.pdf Gain_eq] (Andrew)
 
** Time over threshold analysis - [https://halldweb.jlab.org/DocDB/0042/004295/001/DIRC_tot_slides.pdf Gain_eq] (Andrew)
 
** [https://logbooks.jlab.org/entry/3756210 Correlations between fibers and hit times] (Bill)
 
** [https://logbooks.jlab.org/entry/3756210 Correlations between fibers and hit times] (Bill)
 +
** LED analyses [https://halldweb.jlab.org/wiki/images/0/0a/19Dec.pdf] (Ahmed)
 +
 
* GEM [https://logbooks.jlab.org/entry/3756231 update] and analysis plans discussion
 
* GEM [https://logbooks.jlab.org/entry/3756231 update] and analysis plans discussion
 
* High rate studies:  
 
* High rate studies:  

Revision as of 11:07, 19 December 2019

Meeting Information

GlueX DIRC Meeting
Tuesdays and Thursdays, December 3-19
10:00 am, EDT
Hall D Counting House

Connection Using Bluejeans

  1. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
  2. To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
  3. To join via phone, use one of the following numbers and the Conference ID: 846453895
    • US or Canada: +1 408 740 7256 or
    • US or Canada: +1 888 240 2560
  4. More information on connecting to bluejeans is available.


Useful Links:

Thursday, December 19

  • Reconstruction of runs 70817-71073 almost complete (~8 billion of the 10 billion triggers collected so far):
    • REST, histogram and tree files appearing at: /volatile/halld/home/gxproj7/RunPeriod-2019-11/dirc_monitoring/ver00
    • Plan for data production over downtime
  • Summary of production datasets
  • LED analysis:
  • GEM update and analysis plans discussion
  • High rate studies:
  • Plans for shutdown:
    • LED runs for HV/threshold scans on Friday after beam down
    • LV and HV off over break, but no mechanical changes planned
  • Investigation of North OB in January:
    • Proposal to drain North OB, inspect Bar Box 0 optical coupling to mirror box (misalignment?), inspect mirrors
    • Beam could be back as early as January 7, so we can likely only observe the situation and seal things back up.

Tuesday, December 17

  • Initial data analyses (early runs 70817-70849):
    • Standard halld_recon LUT: [3]
    • FastDIRC: [4]
    • LED analyses north box [5]
  • Total statistics around ~6 billion triggers so far, should get close to statistics we had last Spring (~10 billion total)
  • Upcoming plans:
    • Remaining GEM data with focused FCAL trigger
    • Additional DIRC threshold/gain/HV settings:
    • High rate tests: paths to eliminate DIRC as bottleneck

Thursday, December 12

  • Initial data (70817-70849) reconstruction complete:
    • REST, histogram and tree files appearing at: /volatile/halld/home/gxproj7/RunPeriod-2019-11/dirc_monitoring/ver00
  • Waiting for runs 70937+ to be transferred to the /cache/ disk
  • VERY preliminary first look with FastDIRC
  • Upcoming plans:
    • More GEM data with focused FCAL trigger
    • High rate trigger/DAQ tests, including DIRC (Sasha)
    • CPP test, 1 hr (David)

Tuesday, December 10

  • First field-on data Friday evening: Run 70817+
    • Initial issues with timing now resolved and data processing some plots
    • Initial data reconstruction underway:
      • REST, histogram and tree files appearing at: /volatile/halld/home/gxproj7/RunPeriod-2019-11/dirc_monitoring/ver00
  • Unfortunate data loss before accelerator vacuum issue: Run 70850-70895: https://logbooks.jlab.org/entry/3750309
  • LED Analysis: (Ahmed/Bill/Andrew)
  • Upcoming plans:
    • When beam is back continue with nominal conditions: Threshold = pedestal + 100, equalized gains, HV = 1000 V
    • Dedicated runs with GEM detector included with low trigger rate

Thursday, December 5

  • Collected straight track data in "beam left" position: see correlations with TRD wire chamber and GEM SRS (APV) modules
    • A couple runs with DIRC included for initial tests (70720 and 70721)
  • LED Analysis: (Ahmed/Bill)
  • Upcoming plans:
    • Today/tonight: Straight track data in center and right positions by Friday morning.
    • Friday: Ramp solenoid and setup for DIRC commissioning
    • Weekend: DIRC commissioning with full solenoid field!

Tuesday, December 3

  • Status update from the Hall
  • Plans for straight track data