(Tentative Agenda)
(Tentative Agenda)
Line 41: Line 41:
 
# BCAL Readout
 
# BCAL Readout
 
#* Simulations
 
#* Simulations
#* SiPMs update
+
#* SiPMs: Timeline for RFP and response
 +
#*# Sources sought inquiry ~ completed?
 +
#*# Finalize specifications ~ Feb 22
 +
#*# Submit PR for purchase ~ Feb 26
 +
#*# Issue the Request for Proposals (RFP) ~ Mar 30
 +
#*# Five Samples required prior to proposal evaluation
 +
#*# Evaluation of proposals ~ May
 +
#*# Contract award based on best-value
 +
#*# Project plan is to purchase 4000 units, but may be split between institutions
 +
#*# JLab Award for 20%, with option to purchase remaining 80%
 +
#*# If not purchased by JLab, remaining 80% will be purchased by our collaborators at Universidad Tecnica Federico Santa Maria (Chile)
 +
#*# Note: Two separate procurement agencies will be involved: JLab and USM.
 
#* Light guides. See [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1432 GlueX-doc-1432] Figures 1,2,13,14.
 
#* Light guides. See [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1432 GlueX-doc-1432] Figures 1,2,13,14.
 
#* Geometry for guides, sensors, cooling and cables
 
#* Geometry for guides, sensors, cooling and cables

Revision as of 11:47, 18 February 2010

Teleconference Time: 11:00 a.m. EST

  • ESNET and EVO session
  • Phone in CC F326 is 757-269-6337
  • Phone in the Regina Videoconference Suite is 306-585-4204
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Items for followup from previous meeting(s)

  1. Calibration/Monitoring
    • Geometry for inputing monitoring sources into Bcal
  2. Fcal
    • Specify the number of Rad Hard blocks to writeup a change request to the project.
    • Investigate mechanical issues associated with supporting lead glass on top of shashlik modules (Serguei)
  3. Bcal
    • Specify the normalization and dynamic range for the number of photons/GeV in showers
    • Decide on specific grouping for SiPM sums
    • Possibility of using air gap for SiPM coupling
    • Finalize shapes of "Winston guides"

Documents to Review

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Calibration/Monitoring
    • Light sources in Bcal
  4. FCAL
  5. BCAL
    • Construction Status
    • Fibre tests
  6. BCAL Readout
    • Simulations
    • SiPMs: Timeline for RFP and response
      1. Sources sought inquiry ~ completed?
      2. Finalize specifications ~ Feb 22
      3. Submit PR for purchase ~ Feb 26
      4. Issue the Request for Proposals (RFP) ~ Mar 30
      5. Five Samples required prior to proposal evaluation
      6. Evaluation of proposals ~ May
      7. Contract award based on best-value
      8. Project plan is to purchase 4000 units, but may be split between institutions
      9. JLab Award for 20%, with option to purchase remaining 80%
      10. If not purchased by JLab, remaining 80% will be purchased by our collaborators at Universidad Tecnica Federico Santa Maria (Chile)
      11. Note: Two separate procurement agencies will be involved: JLab and USM.
    • Light guides. See GlueX-doc-1432 Figures 1,2,13,14.
    • Geometry for guides, sensors, cooling and cables
    • Update on USM MOU
  7. Other business

Minutes

Attendees: