Friday Feb 10, 2012 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231
Agenda
- ESH&Q minute - Noise
- Announcements
- Hall D COO
- Health plan
- Space - 4th floor in March Media:floor-plan_4th_floor.pdf
- Welding audit - April
- CAD update
- FDC construction update - Bill
- Tagger update
- Target update
- Electrical - Giles
- Platforms
- Solenoid interface
- Piping systems B31.3 vs B31.9 Media:B31.3_vs_B31.9.docx
Outstanding Action Items
- Update Hall D/Tagger COO - Released