Difference between revisions of "February 25, 2021 CPP Design Meeting/ERR discussion"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Minutes and Action Items)
 
(3 intermediate revisions by the same user not shown)
Line 10: Line 10:
 
** [[Media:CPP_ERR_Report.pdf]]  
 
** [[Media:CPP_ERR_Report.pdf]]  
 
** [[CPP and NPP Readiness Review]]
 
** [[CPP and NPP Readiness Review]]
* Schedule with Resources [[Media:CPP_Schedule_Resources_v2.pdf]]  
+
* MWPC Issues
 +
** [[Media:MWPC_issues.pdf]]         
 +
* Microscope move
 +
** [[Media:Microscope_Move.pdf]]  
 
            
 
            
* Solid Pb target support and installation [[Media:CPP_Target_pic.pdf]]
 
** Target change out concept [[Media:CPP_Target_Mech_concept.jpg]]
 
** Gluex Commissioning Target support stand  [[Media:CPP_Target_Solid_support.jpg]]
 
* Microscope move?
 
 
* Gas system Bubblers - Beni has some
 
* Gas system Bubblers - Beni has some
 
* Design/Procurement status
 
* Design/Procurement status
Line 30: Line 29:
  
 
== Minutes and Action Items ==
 
== Minutes and Action Items ==
 +
* Rory presented mod to orientation of MWPCs - US-DS VHVHVV (last 2 vertical)
 +
** Stephanie will modify 3D model
 +
** Move Microscope 2.65M DS (just to vacuum chamber support stand)
 +
* There are joints in the lead, both o degrees and 45 degrees
 +
** Stephanie to send Lead configuration to Ilya for analysis

Latest revision as of 11:03, 18 March 2021

Meeting Time and Place

Thursday Feb 18, 2021, 2pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon

Agenda

  • Gas system Bubblers - Beni has some
  • Design/Procurement status
  • Things to work out
    • Gas line manifold/bubblers
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements
    • Modified US vacuum system
    • Solid target installation
    • Documentation for ERR
    • Microscope move

Minutes and Action Items

  • Rory presented mod to orientation of MWPCs - US-DS VHVHVV (last 2 vertical)
    • Stephanie will modify 3D model
    • Move Microscope 2.65M DS (just to vacuum chamber support stand)
  • There are joints in the lead, both o degrees and 45 degrees
    • Stephanie to send Lead configuration to Ilya for analysis