# Support structure update (John, Tim, Tom)
 
# Support structure update (John, Tim, Tom)
 
#* Roll fixture testing
 
#* Roll fixture testing
# Bar box transportation
+
# Bar box transportation (Discussion of proposed dates)
#* Discussion of proposed dates
+
#* April 6: complete crate assembly and monitoring system procurement
 +
#* May 4:  complete test of full monitoring and purge system at IU
 +
#* May 24:  load truck at IU and depart for SLAC
 +
#* May 29 - 31:  loading at SLAC
 +
#* June 1:  depart SLAC
 +
#* June 6-7:  unload crate at JLab and transfer boxes to storage rack
 
# Optical box
 
# Optical box
 
#* Status update (Ernie and Jason)
 
#* Status update (Ernie and Jason)

Revision as of 10:50, 8 February 2018

Meeting Information

GlueX DIRC Meeting
Thursday February 8, 2018
10:00 am, EDT
JLab room A110

Connection Using Bluejeans

  1. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
  2. To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
  3. To join via phone, use one of the following numbers and the Conference ID: 846453895
    • US or Canada: +1 408 740 7256 or
    • US or Canada: +1 888 240 2560
  4. More information on connecting to bluejeans is available.

Agenda

  1. Announcements
  2. Support structure update (John, Tim, Tom)
    • Roll fixture testing
  3. Bar box transportation (Discussion of proposed dates)
    • April 6: complete crate assembly and monitoring system procurement
    • May 4: complete test of full monitoring and purge system at IU
    • May 24: load truck at IU and depart for SLAC
    • May 29 - 31: loading at SLAC
    • June 1: depart SLAC
    • June 6-7: unload crate at JLab and transfer boxes to storage rack
  4. Optical box
    • Status update (Ernie and Jason)
      • Box production at Lesker: final production drawings (?)
      • PMT test fixture
      • 3D Model status
      • Other items and quotes
  5. Simulation studies (Maria and Roman)
  6. MAPMT testing (Bill) update
  7. AOB