Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch,  
+
Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch, James Brock, Josh Pierce, Josh Ballard
  
 
==Agenda==
 
==Agenda==
Line 7: Line 7:
 
*Dave's Calcs [[Media:Target calcs1.pdf]] [[Media:Target calcs2.pdf]]
 
*Dave's Calcs [[Media:Target calcs1.pdf]] [[Media:Target calcs2.pdf]]
  
 +
*controls
 
*Cost
 
*Cost
 
*Schedule
 
*Schedule
Line 13: Line 14:
 
==Notes==
 
==Notes==
  
* Target volume of 0.4 l of liquid hydrogen expands to about 1000 l at STP.
+
* Discussed Gas system status, vacuum system, cell and scattering chamber and tasks to be done. The latest P&I diagram was shown and discussed. The following are the results of the discussion;
* Hall B pumps on scattering chamber with turbo pump all the time.
+
** Target group has determined the components for the gas panel and will begin procurements and fabrication of all components associated with it.
* Jim added [http://www.lakeshore.com/products/Cryogenic-Temperature-Sensors/Cernox/Models/Pages/Overview.aspx Lakeshore Cernox temperature sensors] at various heights.
+
** The gas panel (fits in a 19" rack) will be attached to the Target installation cart
** Chris requested that they be removable, to replace defective ones.
+
** Target group will order the 500 gallon H2 tank for outside and take care of piping and instrumentation on the tank
* Chris recommends the [http://www.lakeshore.com/products/cryogenic-temperature-monitors/model-218/Pages/Overview.aspx Lakeshore Model 218] 8-channel temperature monitor read-out unit.
+
** Jim Fochtman will layout the pad requirements for the tank and purge system and submit to facilities for installation.  
* System should be able to liquefy helium-4, taking it down to 3 K.
+
** Jim to  develop inside pipe routing
* Jim will look into adding a relief tube to by-pass normal feed in case of boil off of target liquid.
+
** Jim to look at inside purge tank location (needs to be away from ignition source)
 +
**Josh to test lakeshore controller from target group Monday for compatability with Hall D controls
 +
** Jim to look at procuring chiller for refrig. compressor
 +
** Jim to get with Dave on scattering chamber design.
 +
** Tim to procure vacuum system pump cube (Pfeifer torbo cube)and gauging.
 +
** Chris to send out list of all items needed for monitoring/controlling from PLC system
 +
** Hall D people to discuss what needs to be shut off in hall when target vacuum goes south
 +
** Jim to develop H2 vent details
 +
** One target cell is made, will need to make one more
 +
** Dave to handle pressure system design as the DA
 +
** Look at heat shield next week
 +
** We will have bi-weekly mtgs
 +
** Cold head weight limit maxed out.

Latest revision as of 16:47, 21 February 2013

Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch, James Brock, Josh Pierce, Josh Ballard

Agenda

  • controls
  • Cost
  • Schedule
  • Who does what?

Notes

  • Discussed Gas system status, vacuum system, cell and scattering chamber and tasks to be done. The latest P&I diagram was shown and discussed. The following are the results of the discussion;
    • Target group has determined the components for the gas panel and will begin procurements and fabrication of all components associated with it.
    • The gas panel (fits in a 19" rack) will be attached to the Target installation cart
    • Target group will order the 500 gallon H2 tank for outside and take care of piping and instrumentation on the tank
    • Jim Fochtman will layout the pad requirements for the tank and purge system and submit to facilities for installation.
    • Jim to develop inside pipe routing
    • Jim to look at inside purge tank location (needs to be away from ignition source)
    • Josh to test lakeshore controller from target group Monday for compatability with Hall D controls
    • Jim to look at procuring chiller for refrig. compressor
    • Jim to get with Dave on scattering chamber design.
    • Tim to procure vacuum system pump cube (Pfeifer torbo cube)and gauging.
    • Chris to send out list of all items needed for monitoring/controlling from PLC system
    • Hall D people to discuss what needs to be shut off in hall when target vacuum goes south
    • Jim to develop H2 vent details
    • One target cell is made, will need to make one more
    • Dave to handle pressure system design as the DA
    • Look at heat shield next week
    • We will have bi-weekly mtgs
    • Cold head weight limit maxed out.