Hall-B Schedule

From GlueXWiki
Revision as of 16:26, 6 July 2006 by Zisis (Talk | contribs)

Jump to: navigation, search

All travel, shipping and task schedule information, in connection to the BCAL beam tests at Hall-B (Sep. 2006) is kept on this page.


Tentative dates for Regina personnel:

Rafael (Aug. 20 - Oct. 5), Blake (Aug 20. - Oct. 5), Zisis (Aug. 20 - Aug. 27, Sep. 20 - Oct. 1), Ioanna (Sep. 20 - Oct. 1), George (Sep. 22 - Oct. 1), Garth (Sep. 22 - Oct. 1)


The Table below shows the GlueX-related items from the most recent Hall-B schedule.

Earliest occupancy: August 16, targeted occupancy: August 22.


ID
Task Name
WorkDurationStartFinish% Work Complete
151
GlueX calorimeter
196 hrs9.5 daysThu 8/3/06Wed 8/16/060%
152
Install calorimeter stand
72 hrs3 daysThu 8/3/06Mon 8/7/060%
3
Doug
24 hrs Thu 8/3/06Mon 8/7/060%
4
Calvin
24 hrs Thu 8/3/06Mon 8/7/060%
10
Crane
24 hrs Thu 8/3/06Mon 8/7/060%
153
Install Bcal support
0 hrs1 dayTue 8/8/06Tue 8/8/060%
154
Install calorimeter
120 hrs5 daysWed 8/9/06Tue 8/15/060%
3
Doug
40 hrs Wed 8/9/06Tue 8/15/060%
4
Calvin
40 hrs Wed 8/9/06Tue 8/15/060%
10
Crane
40 hrs Wed 8/9/06Tue 8/15/060%
155
Install Down Stream Helium Bag
4 hrs4 hrsWed 8/16/06Wed 8/16/060%
2
Steve
4 hrs Wed 8/16/06Wed 8/16/060%
156
SURVEY
44 hrs15.63 daysThu 7/27/06Thu 8/17/060%
157
Survey Frascati magnets
8 hrs8 hrsTue 8/8/06Tue 8/8/060%
12
Survey
8 hrs Tue 8/8/06Tue 8/8/060%
158
Survey Pair Spectrometer
8 hrs1 dayWed 8/9/06Wed 8/9/060%
12
Survey
8 hrs Wed 8/9/06Wed 8/9/060%
159
Survey GlueX calorimeter
8 hrs1 dayWed 8/16/06Thu 8/17/060%
12
Survey
8 hrs Wed 8/16/06Thu 8/17/060%
160
Survey Target
8 hrs1 dayThu 7/27/06Fri 7/28/060%
12
Survey
8 hrs Thu 7/27/06Fri 7/28/060%