Hall-B Schedule

From GlueXWiki
Revision as of 15:15, 15 August 2006 by Staylor (Talk | contribs)

Jump to: navigation, search

All travel, shipping and task schedule information, in connection to the BCAL beam tests at Hall-B (Sep. 2006), is kept on this page.


  • Tentative dates for Regina personnel: Rafael (Aug. 19 - Oct. 3), Blake (Aug 19. - Oct. 3), Kathryn (Aug. 19 - Aug. 26), Zisis (Aug. 19 - Aug. 26, Sep. 20 - Oct. 1), Ioanna (Sep. 20 - Oct. 1), George (Sep. 22 - Oct. 1), Garth (Sep. 22 - Oct. 1)
  • Tentative dates for IU personnel: Eric (Aug. 20 - Aug.27)
  • Earliest occupancy: August 16, targeted occupancy: August 22.
  • Installation_Procedures: craning (1 day), bolting (1 day), survey (1 day), PMT mounting (1 day), cosmics (1-2 weeks)
  • Tentative dates for IU BCAL Cart Shipment: Ship Aug. 17-18 for arrival on Aug. 21
  • Tentative dates for Regina Module Shipment: Ship Aug. 13-14 for arrival on Aug. 21
  • Tentative dates for CUA personel: Dan Sober (Sep. 13-14, Sep. 20-Oct. 1), Franz Klein (?), Joe Santoro (?)
  • Tentative dates for OU personnel: Simon Taylor (Sep.5-Oct. 1)

The Table below shows the GlueX-related items from the most recent Hall-B schedule.


ID
Task Name
WorkDurationStartFinish% Work Complete
151
GlueX calorimeter
196 hrs9.5 daysThu 8/3/06Wed 8/16/060%
152
Install calorimeter stand
72 hrs3 daysThu 8/3/06Mon 8/7/060%
3
Doug
24 hrs Thu 8/3/06Mon 8/7/060%
4
Calvin
24 hrs Thu 8/3/06Mon 8/7/060%
10
Crane
24 hrs Thu 8/3/06Mon 8/7/060%
153
Install Bcal support
0 hrs1 dayTue 8/8/06Tue 8/8/060%
154
Install calorimeter
120 hrs5 daysWed 8/9/06Tue 8/15/060%
3
Doug
40 hrs Wed 8/9/06Tue 8/15/060%
4
Calvin
40 hrs Wed 8/9/06Tue 8/15/060%
10
Crane
40 hrs Wed 8/9/06Tue 8/15/060%
155
Install Down Stream Helium Bag
4 hrs4 hrsWed 8/16/06Wed 8/16/060%
2
Steve
4 hrs Wed 8/16/06Wed 8/16/060%
156
SURVEY
44 hrs15.63 daysThu 7/27/06Thu 8/17/060%
157
Survey Frascati magnets
8 hrs8 hrsTue 8/8/06Tue 8/8/060%
12
Survey
8 hrs Tue 8/8/06Tue 8/8/060%
158
Survey Pair Spectrometer
8 hrs1 dayWed 8/9/06Wed 8/9/060%
12
Survey
8 hrs Wed 8/9/06Wed 8/9/060%
159
Survey GlueX calorimeter
8 hrs1 dayWed 8/16/06Thu 8/17/060%
12
Survey
8 hrs Wed 8/16/06Thu 8/17/060%
160
Survey Target
8 hrs1 dayThu 7/27/06Fri 7/28/060%
12
Survey
8 hrs Thu 7/27/06Fri 7/28/060%