Hall D MEDCON5 Operations Resumption Status

From GlueXWiki
Revision as of 08:12, 5 June 2020 by Whitey (Talk | contribs) (Introduction)

Jump to: navigation, search

Introduction

Jefferson Lab will be going into MEDCON5 status on Monday June 8 with the expectation of resuming beam delivery to the Halls in July.

Everyone is to perform the Health Self Certification Test using the JLAB provided card daily before entering JLAB property. The results must be reported to your supervisor if your supervisor is on sight. Otherwise it is the honor system

Anyone coming into Hall D must have the approval of the Hall D Group Leader, Work Coordinator or Engineer.

The COVID-19 Pandemic Controls OSP must be read and understood prior to coming to JLAB

SAF003 COVID-19 Hazard Awareness and Controls must be completed

Read and sign the general Pre-Job Check List for COVID-19 that will be posted in the counting house

Complete and sign (persons performing task and their supervisor) the Pre-job checklist from the COVID-19 OSP for each task for which there is a written procedure before starting. The signed copy is to be posted at the job site.


Access

General Timing of Work in the Hall

Immediate Return June 8

  1. Mark Stevens and Josh Foyles will return to ready the Hall D complex for personnel to return to get equipment ready for beam.

First Tier - June 10?

2nd Tier - June 16?

3rd Tier - June 19?

References

This is was initially based on the shutdown checklists.

File:HCO - Hall D Electronics Hall D Shutdown Checklist.pdf
File:HCO - Hall D Mechanical Hall D Shutdown Checklist.pdf
File:HCO - Hall D Solenoid Hall D Shutdown Checklist.pdf
File:HCO - ENP Target Hall D Shutdown Checklist.pdf