Hall D MEDCON5 Operations Resumption Status

From GlueXWiki
Revision as of 08:25, 5 June 2020 by Whitey (Talk | contribs) (Introduction)

Jump to: navigation, search

Introduction

Jefferson Lab will be going into MEDCON5 status on Monday June 8 with the expectation of resuming beam delivery to the Halls in July. There will be a gradual ramp up of activity in the Hall D complex over several weeks. On June 8th, a limited staff will come in to ready the areas for personnel return to conform to JLAB requirements and to ensure the risk to personnel is as low as reasonably possible. Other tasks (and associated personnel) will be accomplished in Tiers in order to limit the amount of personnel in any given area and ensure the 6' distancing can be maintained. There is currently no work authorized in Hall D which requires this distancing to be violated. The Hall D complex will be set up to have one way traffic to minimize chance encounters. The description of these set up can be found in the Hall D Resumption Plan (insert here)

Access

In order to access the JLAB property, you must have your supervisors approval. Several actions must be completed prior to starting work;

Everyone is to perform the Health Self Certification Test using the JLAB provided card daily before entering JLAB property. The results must be reported to your supervisor if your supervisor is on sight. Otherwise it is the honor system

Anyone coming into Hall D must have the approval of the Hall D Group Leader, Work Coordinator or Engineer.

Sign in on the board at the entrance to the Counting House

The COVID-19 Pandemic Controls OSP must be read and understood prior to coming to JLAB (insert link here)

SAF003 COVID-19 Hazard Awareness and Controls must be completed (insert link here)

Read and sign the general Pre-Job Check List for COVID-19 that will be posted in the counting house

Complete and sign (persons performing task and their supervisor) the Pre-job checklist from the COVID-19 OSP for each task for which there is a written procedure before starting. The signed copy is to be posted at the job site.

General Timing of Work in the Hall

Immediate Return June 8

  1. Mark Stevens and Josh Foyles will return to ready the Hall D complex for personnel to return to get equipment ready for beam.

First Tier - June 10?

2nd Tier - June 16?

3rd Tier - June 19?

References

This is was initially based on the shutdown checklists.

File:HCO - Hall D Electronics Hall D Shutdown Checklist.pdf
File:HCO - Hall D Mechanical Hall D Shutdown Checklist.pdf
File:HCO - Hall D Solenoid Hall D Shutdown Checklist.pdf
File:HCO - ENP Target Hall D Shutdown Checklist.pdf