* Preparation for mass production of FCAL2 modules -- Sasha
 
* Preparation for mass production of FCAL2 modules -- Sasha
 +
** Getting summer students involved in the project. Vaccinated students will be permitted to the lab according to the communication with Brian Hanlon (still to be checked). Not a problem to get 5 - 6 students involved ([https://halldweb.jlab.org/detectors/fcal2/module_fabrication/task_list/task_list_fcal2_fabrication_v2.pdf List of possible tasks]).
 +
** Chris continues brazing brass straps. The quality has been improved. We have many brass assemblies now.
 +
** DSG:
 +
***  About 700 ESR foils (SICCAS) have been preshaped. Start preshaping foils for CRYTUR crystals (after 900 foils for SICCAS are produced). Need new cutting template.
 +
***  Crystal wrapping is very slow, only about 15 crystals have been wrapped during this week.
 +
** Production of Silicon cookies at the GWU [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/4_8_22/image_50394113.JPG]. See Olga's report. Contract with the GWU is under preparation.
 +
** Igal: continues wrapping ESR for crystals and Tedlar
 +
** Procurement of spare PMTs and sockets:  no price increase [https://halldweb.jlab.org/detectors/fcal2/pmt/4125_quotes_fcal_04_06_22.pdf]. Submitted PR for 100 PMTs and 200 sockets; not clear when it will be signed.
 
* Module fabrication  -- Sasha
 
* Module fabrication  -- Sasha
 +
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf  Modules fabricated by Arshak and Sasha] [https://docs.google.com/document/d/1upI9M_RNR4qipzwg-SmxmzkqoCDU294x7Y3jT5M6DVY/edit (list on Google Drive)] (grand total 290)
 +
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/4_8_22/modules_in_tedf_4_8_22.jpg  Fabricated modules in TEDF ]
 +
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ]
 +
* Cable distribution of the FCAL insert -- Sasha
 +
** Connection of LV cables to the PMT base [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/4_15_22/lv_cables.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/4_15_22/lv_cables2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/4_15_22/lv_cables1.jpg]
 +
** [https://halldweb.jlab.org/wiki/images/d/d3/FCAL2_Readout_Layout.pdf Draft of the cable distribution in the FCAL dark room] (meeting with Fernando and Tim)
 +
** Submitted PR for procurement of LEMO (signal) connectors (Chris and Fernando)
 
* Light Monitoring System -- Arshak
 
* Light Monitoring System -- Arshak
 
**https://halldweb.jlab.org/DocDB/0055/005557/001/lms_update_04_14_22.pdf
 
**https://halldweb.jlab.org/DocDB/0055/005557/001/lms_update_04_14_22.pdf
Line 13: Line 28:
 
* Simulations
 
* Simulations
 
** [[Plots for informal island algorithm discussion]] -- Simon
 
** [[Plots for informal island algorithm discussion]] -- Simon
 +
 +
=Minutes=
 +
Attendees: Bill, Zisis, Sasha, Olga, Igal, Liping, Arshak, Tegan, Jon, Susan, Tim B., Tim W., Jane, S.T.
 +
* Situation for students coming to JLab in the summer is becoming clearer
 +
** Lab is able to pay for lodging and per diem, maybe transportation
 +
** Phil will send 2 students, GWU has 3 students + 1 from community college, Liping looking at applications from 4 students, 2 students from URegina possible
 +
** Most pressing task is crystal wrapping; Sasha could also have students work on tagger hodoscope repairs or COMCAL refurbishment
 +
* Since we are using 16 ESR jigs borrowed from NPS, we agreed to produce foils for NPS as their fabrication ramps up
 +
* GWU working on silicon cookies -- currently done by Olga, but soon a student will be doing this
 +
* FCAL2 module count now up to 290
 +
* Discussions with Tim W. and Fernando regarding cabling in the dark room taking place
 +
** Space for low voltage cables tight but seems manageable
 +
** Need to pay attention to strain relief and ease of access
 +
** Made 4x4 array to test cabling
 +
* Arshak continues to work on LMS development
 +
** Plexiglas delivered from machine shop attenuates injected light to much -- Arsak ordered new cast acrylic plate from outside vendor
 +
** Some LEDs arrived but integrating sphere is going through procurement process
 +
** Looking at using connectors for light injection as opposed to gluing fibers directly to plastic sheet
 +
*** 3D printed vs commercial connectors?
 +
** How to hold in place in front of insert?  Discussed angle holders on 4 sides
 +
** 4-piece plexiglas in front of existing FCAL needs to be modified
 +
* After the meeting we discussed the state of the island algorithm reconstruction and the isolation of the η→π0γγ channel
 +
** Simon's results don't completely agree with things seen by other people -- not clear tweaking parameters helps in the final analysis
 +
** TOF veto is important, but backsplash from showers from photons in the FCAL could be a problem

Latest revision as of 08:01, 18 April 2022

Meeting time and location=

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation for mass production of FCAL2 modules -- Sasha
    • Getting summer students involved in the project. Vaccinated students will be permitted to the lab according to the communication with Brian Hanlon (still to be checked). Not a problem to get 5 - 6 students involved (List of possible tasks).
    • Chris continues brazing brass straps. The quality has been improved. We have many brass assemblies now.
    • DSG:
      • About 700 ESR foils (SICCAS) have been preshaped. Start preshaping foils for CRYTUR crystals (after 900 foils for SICCAS are produced). Need new cutting template.
      • Crystal wrapping is very slow, only about 15 crystals have been wrapped during this week.
    • Production of Silicon cookies at the GWU [1]. See Olga's report. Contract with the GWU is under preparation.
    • Igal: continues wrapping ESR for crystals and Tedlar
    • Procurement of spare PMTs and sockets: no price increase [2]. Submitted PR for 100 PMTs and 200 sockets; not clear when it will be signed.
  • Module fabrication -- Sasha
  • Cable distribution of the FCAL insert -- Sasha
  • Light Monitoring System -- Arshak
  • COMCAL tests, TAC running, etc. -- Sasha
  • Data analysis
  • Simulations

Minutes

Attendees: Bill, Zisis, Sasha, Olga, Igal, Liping, Arshak, Tegan, Jon, Susan, Tim B., Tim W., Jane, S.T.

  • Situation for students coming to JLab in the summer is becoming clearer
    • Lab is able to pay for lodging and per diem, maybe transportation
    • Phil will send 2 students, GWU has 3 students + 1 from community college, Liping looking at applications from 4 students, 2 students from URegina possible
    • Most pressing task is crystal wrapping; Sasha could also have students work on tagger hodoscope repairs or COMCAL refurbishment
  • Since we are using 16 ESR jigs borrowed from NPS, we agreed to produce foils for NPS as their fabrication ramps up
  • GWU working on silicon cookies -- currently done by Olga, but soon a student will be doing this
  • FCAL2 module count now up to 290
  • Discussions with Tim W. and Fernando regarding cabling in the dark room taking place
    • Space for low voltage cables tight but seems manageable
    • Need to pay attention to strain relief and ease of access
    • Made 4x4 array to test cabling
  • Arshak continues to work on LMS development
    • Plexiglas delivered from machine shop attenuates injected light to much -- Arsak ordered new cast acrylic plate from outside vendor
    • Some LEDs arrived but integrating sphere is going through procurement process
    • Looking at using connectors for light injection as opposed to gluing fibers directly to plastic sheet
      • 3D printed vs commercial connectors?
    • How to hold in place in front of insert? Discussed angle holders on 4 sides
    • 4-piece plexiglas in front of existing FCAL needs to be modified
  • After the meeting we discussed the state of the island algorithm reconstruction and the isolation of the η→π0γγ channel
    • Simon's results don't completely agree with things seen by other people -- not clear tweaking parameters helps in the final analysis
    • TOF veto is important, but backsplash from showers from photons in the FCAL could be a problem