Difference between revisions of "JEF meeting, February 21, 2020"

From GlueXWiki
Jump to: navigation, search
(Agenda)
 
Line 34: Line 34:
 
*** 350um Mu metal shield qty 1620 - Purchase req submitted, waiting for order to be placed (out for competitive bid)
 
*** 350um Mu metal shield qty 1620 - Purchase req submitted, waiting for order to be placed (out for competitive bid)
 
*** Acrylic light guides - on hold until a decision is made on diameter
 
*** Acrylic light guides - on hold until a decision is made on diameter
 +
 +
 +
=Minutes=
 +
Attendees:  Josh, Karthik, Zisis, Arshak, Igal, Susan, Jane, Tim B., Tim D., Jon Z., Sasha, S.T.
 +
* The clean room in the TEDF is ready to go!  Safety documentation is in the works.
 +
* 150 more PMTs arrived -- need dimension checks
 +
* Shanghai Ceramics has still not shipped the crystals, although it sounds like things are reopening there.
 +
** We have money for 500 more crystals but it looks like a new contract will be needed
 +
* Still trying to arrange contract with Wuhan (original was rejected due to appearance of duplication of effort).
 +
* We finalized the light guide design:  will go with 18 mm diameter standard tube size, connect with crystal with cookie for ease of maintenance.
 +
** Suggestion was made to test 3x3 array with beam
 +
** Can also use existing setup in PS arm
 +
* Dividers:  Chris S. working on procuring parts and constructing several modified dividers (1-2 week time frame)
 +
** Instrument part of COMCAL with 3x, 6x amplification modifications, need to measure resolution
 +
* Gluex/JEF up for jeopardy this PAC -- need to put together an update

Latest revision as of 10:23, 24 February 2020

Meeting time and location= 10:00 am EST (JLab time) CC-F226


Connection instructions

We are using BlueJeans Video/Audio conferencing. Our meeting ID number is 992533564. Click "Expand" for more details.

  • Make sure you have created a BlueJeans account via your JLab CUE account using this link:
  • If connecting via Web Browser: click this link (no passcode is needed):
  • If connecting via Phone: Dial one of the following numbers and then enter the meeting ID above and hit "#" or "##"
  • If connecting via Polycom unit:
    • Dial 199.48.152.152 or bjn.vc
    • Enter meeting ID above

Agenda

  • Infrastructure update (TEDF, light yield setup, etc.)
  • Status of the crystal production (SICCAS)
  • Preparation for module fabrication
    • Parts/Materials to be supplied by Tim
      • Brass straps (.001" x 0.5" x 3400') - received and in cleanroom
      • G10 PMT holders - qty 1650 - received and in cleanroom
      • Kapton film 25um Qty (300 ft) HN Kapton film x 12" wide - received and in cleanroom
      • Qty (1) roll 1" 25um thick Kapton tape (63um with adhesive) - received and in cleanroom
      • 66813-B-03501 brass upstream plate - 500 on order - remainder will be done by CMU later
      • 66813-B-03503 brass jacking plate - 500 on order - remainer to be made by CMU later
      • 1020 Steel PMT shield/Housing qty 1620 - being fabricated by CMU
      • 350um Mu metal shield qty 1620 - Purchase req submitted, waiting for order to be placed (out for competitive bid)
      • Acrylic light guides - on hold until a decision is made on diameter


Minutes

Attendees: Josh, Karthik, Zisis, Arshak, Igal, Susan, Jane, Tim B., Tim D., Jon Z., Sasha, S.T.

  • The clean room in the TEDF is ready to go! Safety documentation is in the works.
  • 150 more PMTs arrived -- need dimension checks
  • Shanghai Ceramics has still not shipped the crystals, although it sounds like things are reopening there.
    • We have money for 500 more crystals but it looks like a new contract will be needed
  • Still trying to arrange contract with Wuhan (original was rejected due to appearance of duplication of effort).
  • We finalized the light guide design: will go with 18 mm diameter standard tube size, connect with crystal with cookie for ease of maintenance.
    • Suggestion was made to test 3x3 array with beam
    • Can also use existing setup in PS arm
  • Dividers: Chris S. working on procuring parts and constructing several modified dividers (1-2 week time frame)
    • Instrument part of COMCAL with 3x, 6x amplification modifications, need to measure resolution