Attendees: Igal,Bill,Tegan,Arshak,Jon,Liping,Jane,Olga,Tim B.,Sasha,S.T.
 
Attendees: Igal,Bill,Tegan,Arshak,Jon,Liping,Jane,Olga,Tim B.,Sasha,S.T.
 
* Arshak has finished cleaning up the clean room in preparation for module construction
 
* Arshak has finished cleaning up the clean room in preparation for module construction
** Module construction to resume mass production next week: maybe 4-5 a day?
+
* Arshak and Sasha are making silicon cookies
** Detector support group getting involved (2 people + possibly more):  ESR pre-shaping and module wrapping
+
** 36 cookies are ready, we have just loaded fixture to produce another set. We have enough to start production
* Arshak working on making silicon cookies and LMS (tools ready to go)
+
* Arshak started working on the LMS (tools ready to go)
 +
* Sasha
 +
:: -had a meeting with the detector support group (DSG) and discussed pre-shaping. They may start
 +
working on this during next week (TDB). Another project project is wrapping crystals. Hopefully 2 people
 +
from the DSG will be involved soon.
 +
:: - coordinated with Tim purchasing some equipment (vacuum chamber and pump, air flow box) to set up production
 +
of Silicon cookies at GWU. 
 +
:: - loan agreement with GWU is ready. Will send it out for signatures when ordered equipment arrives to the lab
 +
:: Eugen got permission for Olga to come to the lab.
 
* Olga to come to lab, will work on silicon cookies
 
* Olga to come to lab, will work on silicon cookies
 
* Chris S. has all parts for construction of new PMT dividers using Fernando's design
 
* Chris S. has all parts for construction of new PMT dividers using Fernando's design

Revision as of 19:23, 28 January 2022

Meeting time and location

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Module fabrication
  • Light Monitoring System
  • COMCAL tests, TAC running, etc.
  • Data analysis
  • Simulations
    • Checking the 5 degree inefficiency for phi-related problems: [1]

Minutes

Attendees: Igal,Bill,Tegan,Arshak,Jon,Liping,Jane,Olga,Tim B.,Sasha,S.T.

  • Arshak has finished cleaning up the clean room in preparation for module construction
  • Arshak and Sasha are making silicon cookies
    • 36 cookies are ready, we have just loaded fixture to produce another set. We have enough to start production
  • Arshak started working on the LMS (tools ready to go)
  • Sasha
-had a meeting with the detector support group (DSG) and discussed pre-shaping. They may start

working on this during next week (TDB). Another project project is wrapping crystals. Hopefully 2 people from the DSG will be involved soon.

- coordinated with Tim purchasing some equipment (vacuum chamber and pump, air flow box) to set up production

of Silicon cookies at GWU.

- loan agreement with GWU is ready. Will send it out for signatures when ordered equipment arrives to the lab
Eugen got permission for Olga to come to the lab.
  • Olga to come to lab, will work on silicon cookies
  • Chris S. has all parts for construction of new PMT dividers using Fernando's design
    • To build a few for bench testing starting maybe next week
  • Loan agreement with GWU ready to go
    • Equipment for silicon cookie production
    • PMT divider testing
  • Tegan presented some photon gun studies focusing on the dip in efficiency at 5 degrees for FCAL2
    • Still not clear what is causing the dip
  • Jon reported for Azizah that there appears to be an issue (lower efficiency compared to studies by other people)with her samples of events at fixed φ=0 degrees