*'''Preparation of parts for ECAL''' -- Sasha  
 
*'''Preparation of parts for ECAL''' -- Sasha  
 
** - signal cables: 1360 short cables, all long cables are ready
 
** - signal cables: 1360 short cables, all long cables are ready
** - HV cables: 140 short cables, 36 long cables are in production
+
** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
 
** - LV cables: ordered
 
** - LV cables: ordered
  

Revision as of 21:56, 12 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: 1360 short cables, all long cables are ready
    • - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    • - LV cables: ordered
  • Testing of PMT dividers -- Sasha / Vlad
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation