Difference between revisions of "JEF meeting, October 13, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
Line 8: Line 8:
 
** - signal patch panels are ready
 
** - signal patch panels are ready
 
** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
 
** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
** - HV patch panels: need to check cable connections for
+
** - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
 
** - LV cables: ordered
 
** - LV cables: ordered
 +
** - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Light monitoring system'''
 
* '''Light monitoring system'''
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''

Revision as of 22:03, 12 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: 1360 short cables, all long cables are ready
    • - signal patch panels are ready
    • - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    • - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    • - LV cables: ordered
    • - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
  • Testing of PMT dividers -- Sasha / Vlad
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation