*'''Preparation of parts for ECAL''' -- Sasha  
 
*'''Preparation of parts for ECAL''' -- Sasha  
 
*# - signal cables: 1360 short cables, all long cables are ready
 
*# - signal cables: 1360 short cables, all long cables are ready
** - signal patch panels are ready
+
*# - signal patch panels are ready
 
*# - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
 
*# - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
 
*# - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
 
*# - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)

Revision as of 22:06, 12 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    1. - signal cables: 1360 short cables, all long cables are ready
    2. - signal patch panels are ready
    3. - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    4. - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    5. - LV cables: ordered, lead time unclear
    6. - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
  • Testing of PMT dividers -- Sasha / Vlad
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation