*# - LV cables: ordered, lead time unclear
 
*# - LV cables: ordered, lead time unclear
 
*# - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
 
*# - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
 +
*# - Optical fibers: received all
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 +
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Light monitoring system'''
 
* '''Light monitoring system'''
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''

Revision as of 22:08, 12 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    1. - signal cables: 1360 short cables, all long cables are ready
    2. - signal patch panels are ready
    3. - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    4. - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    5. - LV cables: ordered, lead time unclear
    6. - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
    7. - Optical fibers: received all
  • Testing of PMT dividers -- Sasha / Vlad
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation