Difference between revisions of "Jan 12, 2011 SiPM Electrical and Cooling"

From GlueXWiki
Jump to: navigation, search
(Action Items from previous meetings)
(Action Items from previous meetings)
Line 3: Line 3:
 
# U-boards need to be ordered for the mini-Bcal (Chris)
 
# U-boards need to be ordered for the mini-Bcal (Chris)
 
# Cables need to be ordered for the SiPM production test setup (Chris)
 
# Cables need to be ordered for the SiPM production test setup (Chris)
# Values of trim resistors for nominal operation to Chris (Jack)
+
# Values of trim resistors for nominal operation to Chris (Jack). Chris to add them to the BOM.
  
 
== Tentative Agenda ==
 
== Tentative Agenda ==

Revision as of 19:14, 5 January 2012

Action Items from previous meetings

  1. U-boards need to be ordered for the mini-Bcal (Chris)
  2. Cables need to be ordered for the SiPM production test setup (Chris)
  3. Values of trim resistors for nominal operation to Chris (Jack). Chris to add them to the BOM.

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (everyone)
  5. Mechanical assembly (Scot)
  6. Mechanical (Jim)
  7. Mechanical drawings (Chuck)
  8. Temperature compensation (Jack)
  9. Preamp-summing (Fernando/Chris)
  1. SiPM testing (Ivan)

Minutes

Attending: